News
Release NDDC’s Withheld Funds, Groups Implore IOCs
The Niger Delta Indigenous Contractors Association (NDICA) and Contractors Association of NDDC have called on International Oil Companies (IOCs) in the Niger Delta region to release all unpaid funds accruing to the Niger Delta Development Commission (NDDC) since its inception in 2000.
The indigenous contractors of NDDC made the call in a joint statement after their review meeting in Port Harcourt, Rivers State, on their visit to the Minister of Niger Delta Affairs, Umana Umana, in Abuja, recently.
It was learnt that the commission is entitled to a statutory three per cent fund from IOCs’ annual profits for the operations of the agency in the region.
Earlier, Secretary General of the NDICA, Prince Sodinie, recalled that the group was founded in 2000 with the objective of proper coordination and monitoring of contracts and execution by indigenous contractors for quality delivery in accordance with the contract specification.
In a resolution signed by the acting National President, Dressman Darlington, the contractors, called on the multinational oil companies to remit the funds to the Federal Government interventionist agency to enable it to carry out its statutory responsibilities in the region.
The groups expressed confidence in the minister of Niger Delta Affairs to address the lingering issues affecting the oil-rich region.
“We are calling on the IOCs to, as a matter of urgency, release monies due for the NDDC to enable the agency to live up to its responsibilities to her contractors.”
Meanwhile, the groups have alleged that the commission has been owing the contractors hundreds of billions of naira, spanning a period of over six years.
According to them, efforts to recover the debt under the immediate past minister proved abortive.
The groups during their recent visit to the current minister expressed their ordeal since the debts, which they said included the death of their members, loss of key assets to banks, financial institutions, inability to fund their children’s education and other issues.
They appealed to him (Umana) to look into their plight and save what is left of them and their families.
“We, both associations, had extensive discussions with the Honourable Minister for Niger Delta Affairs, Obong Umana Umana, during our visit to Abuja, on August 10, 2022,” the stated.
“The essence of our discussions bordered on the payment of contractors of the NDDC and we wish to state categorically that we are very pleased with the warm embrace to which we were received by the minister.
“The minister’s body language has shown that he is, indeed, a statesman that has the interest of the Niger Delta region and the Niger Delta people at heart.
“It is worthy of note that he showed empathy in the unfortunate situation of the contractors which has led to the death of so many of them and has promised to find a lasting solution to the issues presented before him.
“Based on the foregoing, we wish to call on all contractors, consultants, service providers and pressure groups of the commission to be patient with the administration of Obong Umana Umana.
“We express high optimism in the ability of the minister to return Niger Delta back on the part development and progress.”
Also, the patron of the group and former senator in Bayelsa State, John Brambaifa, has appealed to the aggrieved contractors, consultants and other groups with the agency over the delayed contract payments, to sheathe their swords and give the new minister time to settle all lingering issues amicably.
News
NGO-ATLANTIC-OYOROKOTO ROAD’LL UNLOCK COASTAL PROSPERITY FOR RIVERS – FUBARA
Rivers State Governor, Sir Siminalayi Fubara, has described the ongoing construction of the brand new 13.52-kilometre Ngo-Atlantic-Oyorokoto Road as a bold and visionary effort by his administration to open up the coastal region for economic growth and harness the full potential of the state’s blue economy.
The Governor made this remark during an inspection visit to the project site in Andoni Local Government Area. The road, being constructed by Monier Construction Company (MCC), cuts through challenging coastal terrain and leads to a newly identified beachfront facing the Atlantic Ocean.
Governor Fubara explained that while the original plan was to construct a road leading to Oyorokoto Town and its popular beach, his administration decided to expand the project to create an entirely new route that would open access to another pristine beachfront.
“We are doing another inspection today. This particular one is a virgin road, 13.52 kilometres of a new pathway to the blue economy,” Governor Fubara stated.
“Initially, we were constructing a road to Oyorokoto Beach, one of the finest tourist centres in this area. But as we progressed, we discovered another beach directly facing the Atlantic Ocean. It became clear that we shouldn’t limit development to just one site. We want to harness this new beach front as part of our broader plan to develop the blue economy.”
The Governor emphasised that the project, once completed, will not only improve access to coastal communities but also stimulate tourism and economic activities, boosting revenue for Rivers State.
Describing the area’s difficult terrain as challenging, he commended the contractor for its dedication, and expressed confidence that the road would be completed and commissioned by March next year.
“You can see for yourself, it’s a brand-new road in a very difficult terrain, just like the one we saw yesterday. But I strongly believe we will overcome it. From what we’ve seen today, the contractor, MCC, is doing their best, and by next year, hopefully by March, we’ll have the cause to commission this project and give God all the glory,” the Governor affirmed.
Governor Fubara also visited Opobo/Nkoro Local Government Area to assess the progress of work on the Epellema axis of the ongoing 5.2km Kalaibiama-Epellema road project featuring a 450-meter bridge.
News
FUBARA HAILS PROGRESS OF WORK ON TRANS-KALABARI ROAD
Rivers State Governor, Sir Siminalayi Fubara, has expressed satisfaction with the level of progress recorded on the ongoing Trans-Kalabari Road project, revealing that about 75 percent of the critical piling work has been completed.
Governor Fubara made this known while addressing journalists after an on-the-spot inspection of the 12.5-kilometre road project, which will connect the state capital to several Kalabari communities across the sea.
The Governor rode on a boat from a jetty at Rumuolumeni in Obio/Akpor Local Government Area through the rivers and creeks on the project route during the inspection.
The project was awarded to Lubrik Construction Company Limited, on May 15, 2024, with an initial 32-month completion timeline.
The Governor said the visit was aimed at verifying reports from the Ministry of Works regarding the project’s advancement. He commended the contractors for their dedication, and described the progress as “a true reflection of hard work and commitment to excellence.”
“The first phase of the project takes us to Bakana, and features four major river-crossing bridges and nearly five deck-on-pile structures. The terrain is difficult, and the engineering work required is complex. But to the glory of God, I can confirm that the reports I’ve been receiving are accurate. Almost 75% of the piling job, which is the most critical part of the project, has been achieved,” Governor Fubara said.
He emphasised that the Trans-Kalabari Road is one of the most technically demanding infrastructure projects in the state due to its challenging marine terrain but reaffirmed his administration’s resolve to deliver it on schedule.
Governor Fubara highlighted the strategic importance of the road in connecting the Kalabari Kingdom to Port Harcourt, and stimulating economic growth across riverine communities.
“This is a key project that will turn around the lives of the Kalabari people immediately it is concluded. By the grace of God, in the next six months, if we return here for inspection, we might be driving across the bridge,” he said.
Governor Fubara assured Rivers people that his administration remains focused on delivering transformative infrastructure projects that will improve lives and bring lasting development to rural communities.
“We have made a promise to our people to embark on projects that will change lives and bring development, and this is a testament to that commitment,” he added.
News
RSG EXPRESSES CONCERN OVER FLOODING IMPACT, EROSION
The Governor of Rivers State, Sir Siminalayi Fubara, says that the impact of flooding and erosion on the inhabitants of Rivers State, especially those living in coastal communities, are of great concerns to the government.
Governor Fubara lamented the consequences of flood on both human and biotic life, which sometimes lead to loss of life, property, and degradation of the environment.
The Governor made the remark in Port Harcourt during the launch of a book titled, ‘Coastal Zone Flooding And Erosion in Developing Communities, Principles, Cases and Strategies,” written by Emeritus Prof. Wiston Bell-Gam.
According to the Governor, who was represented by the Secretary to the State Government, Hon. Benibo Anabraba, his administration, would continue to undertake and encourage adaptation strategies to combat flooding.
In his words: “The Rivers State Government will continue to undertake and encourage adaptation strategies, such as construction of seawalls and breakers, canals and channels, restoring coastal ecology and ecosystem for coastal resilience and where necessary, the relocation of communities on the coastline.
“These issues are currently receiving the much needed attention and intervention by the recent approval of the construction of shoreline protection along the coastlines of more than five communities in Ogba/Egbema/Ndoni and Opobo/Nkoro LGAs respectively.”
“It is important that as stakeholders in the protection and preservation of marine environment, we all act and advocate for mitigation strategies such as reduction in emission of Green House Gasses that causes climate change and rise in sea levels. Let us promote the use of clean energy and against fossil fuel.
Governor Fubara further cautioned residents to desist from building on waterways.
“We also need to encourage our people to stop developing buildings on and along natural water courses, indiscriminate sea mining and dredging activities on our coastline without consideration for mangroves and swamps,” he stressed.
He appreciated the author for his advanced contributions to the body of knowledge in both Rivers State and globally.
Also speaking, a former Military Governor of the old Rivers State and Amayanabo of Twon Brass, King Alfred Ditte-Spiff, who was Royal Father at the Event, stated that the book was timely to enable stakeholders manage the challenges of global warming.
“Global warming is real. If it’s not addressed globally, a time will come coastal areas will find themselves under water. The coastline of Nigeria is shocking with many mangroves gone,” he noted.
The Reviewer of the Book, who is also the Vice Chancellor of Olusegun Agagu University of Science and Technology, Ondo State, Prof Temi Ologunorisa, explained that the 14-chapter book is timeous as it fills literary gaps between desire and available knowledge on coastal flood and erosion in developing communities.,
“A major beauty of the book that sets it apart is the detailed consideration of flood and erosion control from around the world,” he stated, adding that the book is based on detailed field investigation.
-
Rivers4 days agoRumuji Crisis Claims One Life, Destroys King’s Palace
-
Sports4 days agoArsenal Continue Impressive Start To Season
-
Maritime4 days agoStakeholders Advocate Water Transport To Decongest Road Transportation
-
News4 days agoIran vows to rebuild stronger nuclear sites
-
Oil & Energy4 days agoFG Reaffirms Commitment To Brass Gas Project
-
Rivers4 days ago
Group Urges Fubara To De-escalate Crisis In Emohua
-
Sports4 days agoBayern Continue Bundesliga Dominance
-
Business4 days agoItakpe Train Derailment: No Casualty Recorded — NRC