Connect with us

News

IOCs Contribute $1bn For Ogoni Clean-Up, FG Confirms

Published

on

International oil companies (IOCs) have so far contributed about $1billion for the implementation of Ogoni clean-up project.
The Minister of Environment, Dr Mohammad Abubakar, made this known during a news briefing organised by the ministry in Abuja on the ongoing clean-up of Ogoniland.
According to Abubakar, the remediation of 21 lots of phase one batch has been cleaned while 17 lots were done by Hydrocarbon Pollution Remediation Project (HYPREP).
He said that 10 out of the 17 lots were closed-out by the National Oil Spill Detection Agency (NOSDRA), adding that the certification sampling of three lots for close-out was completed.
Abubakar said, “While the other three are awaiting certification sampling for close-out by NOSDRA, the remaining five, which are yet to be completed by HYPREP, are at various stages of completion.
“Also, 36 remediation contracts comprising two project activities, namely soil remediation works, 29 lots, and tier two assessments of groundwater works, seven lots, were awarded in February, 2020.
“However, due to the global Coronavirus pandemic in the first and second quarters of 2020, activities preceding mobilisation of these contractors to site were slowed down.
“As at today, nine remediation lots have been completed, and are awaiting NOSDRA certification, and seven other contracts for detailed quantitative environmental risk assessment to determine groundwater conditions in some selected sites, were completed.”
The minister said that the Federal Government inaugurated the construction of six water schemes on March 22 at Khana, Tai and Gokana local government areas of Rivers State.
He said that the sites were Bori/Kpean Water Scheme in Khana Local Government Area, Barako/Bori-Dere/Kpea Dere water scheme in Gokana LGA.
He gave others as Terabo water scheme in Gokana LGA, Korokoro/Nonwa water scheme in Tai LGA, and Alesa and Ebubu/Nsisioken/Ogale water schemes in Eleme LGA.
He said that the rehabilitation and construction works had started in all the sites.
Abubakar said that about 882 youths in the communities were engaged by batch one remediation contractors while additional 1,118 youths were also engaged by batch two remediation contractors.
“Therefore, as at today, a total of 2,000 temporal jobs were created in the course of remediation.”
“The job was across the four LGAs of Ogoniland, besides the numerous indirect jobs that are to be created in the form of trading and support activities,” he said.
Abubakar said that International Institute of Tropical Agriculture (IITA) and the Stakeholders Democracy Network (SDN) trained 15 youths from the four LGAs of Ogoniland.
He said that at the end of the three months intensive training, the trainees fabricated machines used to set up a cassava processing facility at Korokoro, Tai LGA.
Abubakar said that strategy for the restoration and management of degraded mangrove vegetation involved planning, decision making and implementation of the restoration programme.
The minister said that the programme was based on Shoreline Assessment Technique (SCAT) outcome, adding that the SCAT would provide information and data on the extent and depth of contamination.
He said that the SCAT would offer guidance on the most suitable technique for the clean-up of the impacted shoreline to ensure the reduction of ‘environment harm.
He said that the selected technique would ensure environmental benefit for both flora and fauna were achieved.
“The proposed size for the SCAT is 1,000 hectares along the shorelines of creeks and rivers and is categorised into three phases.
“Phase one covers 300 hectares upstream while phase two covers 300 hectares mid-stream and Phase three covers 400 hectares down-stream.
“Each of the phases is achievable within six months of field work. The SCAT process will be undertaken by a team of professionals drawn from the critical stakeholders,” he added.

Continue Reading

News

Be Patient With Us, Diri Tells Bayelsans … Inspects New 60mw IPP …Expresses Confidence In Technical Partners, BECL MD

Published

on

Bayelsa State Governor, Senator Douye Diri has sued for patience on the ongoing installation of the state’s new independent power project.
The Tide gathered that the 60-megawatt gas turbine project, which installation commenced in October this year, was earlier scheduled to be completed by December but suffered logistics related delays.
The governor called on people of the state to have an open mind about the project, which he said now requires a new completion date due to unforeseen challenges.
?
?The Tide further reports that the State’s Chief Executive who undertook an on-the-spot-assessment of the project at Elebele in Ogbia Local Government Area on Wednesday, said like other citizens of the state, he was also disappointed that the December completion deadline could not be met.
However, he stated that his reaction to the delay had been that of understanding rather than being angry as had been noticed, particularly on the social media.
?
?”You can see I’ve  gone round the whole facility. It was based on the working agreement and information available at my disposal that I gave the December date. But as it is with every human endeavor, we must all have an open mind, when it comes to issues, particularly technical matters like this.
?
?”I am as disappointed as any other Bayelsan because I believed that we were going to celebrate the 2025 Christmas with our own independent power, but it turned out not to be so.
?
?”I call on Bayelsans to have an open mind. These technical experts are working virtually 24 hours, but delays like this will certainly come”, he said.
?
He implored the people 9f the state to appreciate the work of the engineers, stressing that a minor mistake was capable of jeopardising the millions of dollars expended on the project.
?
?”For 29 years Bayelsa has been in darkness or has endured epileptic power supply. Now that we are getting close to the day of liberation, some people have become impatient.
“Let us not behave like the proverbial tortoise in the prison for years that asked to be released immediately as the place was smelling the moment he knew it would regain freedom the next day”, the governor added.
?
?The Bayelss Governor gave a thumps up to the technical partners, Jampur Group, and its team on ground as well as the Managing Director of the Bayelsa Electricity Company Ltd, Engr. Olice Kemenanabo, saying they were working round the clock to ensure the job was completed.
?
?”Those who have been following me on this inspection would know that work has not stopped even for one day since it started. I am sure the job is more than 90 per cent complete. So let us hold our fire.
“Engineer Olice, I am not putting you under any pressure. From the reports I have, Olice is one of the best electrical engineers in Nigeria”, governor Diri said.
?
The governor, however, hinted that the government was looking at inaugurating the project during its sixth anniversary in February.
?
The MD of the Bayelsa Electricity Company Limited, Kemenanabo, who also spoke, said the state was on the right track towards actualising the project and assured that the alignment of the entire system, including the gas generator and alternator were on course.
?
He also stated that the remaining two turbines would be delivered to the project site in a few days.
?
?Speaking on behalf of the Jampur Group, Mr. Sherrif Abu-Anif said the company was in good position to meet its own end of the bargain and appreciated the state government for playing its part very well.
By Ariwera Ibibo-Howells, Yenagoa
Continue Reading

News

Akpabio Withdraws All Defamation Suits After Priest’s Sermon 

Published

on

The Senate President, Senator Godswill Akpabio, has directed his lawyers to withdraw all ongoing defamation lawsuits against several individuals, saying he was moved by counsel during a New Year Mass.

Speaking at the Sacred Heart Parish in Uyo, yesterday, Akpabio said he had filed nearly nine lawsuits against individuals he accused of defaming him.

He said, “I had almost nine cases in court against some individuals who defamed me, who lied against me, who slandered my name.

“But I listened to the priest and suddenly realised he was talking to me, so I hereby direct my solicitor to withdraw all lawsuits against them.”

In 2025, Akpabio had filed several high-profile defamation lawsuits, including one against colleague Senator Natasha Akpoti?Uduaghan.

In late 2025, Akpabio filed a N200 billion defamation lawsuit against her over allegations of sexual harassment, which he denied and urged her to substantiate in court.

Earlier in the year, Akpabio’s wife also filed defamation suits against Akpoti?Uduaghan over claims she said had harmed her family’s reputation.

Relations between the two lawmakers soured after Akpoti?Uduaghan accused Akpabio of influencing her suspension from the Senate in March 2025, following her public allegations of misconduct.

The Senator had previously challenged actions taken against her in court, including a N100 billion defamation suit she filed against Akpabio and other defendants over alleged remarks that she said damaged her reputation.

With yesterday’s announcement, Akpabio has formally ended all pending legal disputes arising from defamation claims, signalling closure to the publicised litigations as the year begins.

Continue Reading

News

‘Best Way To Show Gratitude Is To Deliver Tinubu in 2027’

Published

on

Rivers State Governor, Sir Siminalayi Fubara, has declared that the best form of gratitude Rivers people owe President Bola Ahmed Tinubu for protecting the interest of the State is to galvanize massive support for the President in 2027.

 

Fubara disclosed this last Monday during the commissioning of Permanent Secretaries Quarters built by his administration at Elimgbu in Obio Akpor Local Government Area of the State.

 

He said that the State has what it takes to deliver the President during the 2027 general elections.

 

“We’ve taken a decision,our decision is for the good of Rivers State, our decision is to say thank you for the protection we have from Mr President, our decision is to prove that we have what it takes to deliver Mr President.”

 

Fubara expressed delight over the completion of the project,  stating that the initiative was to provide accommodation, a basic need of life  for public servants in the state to improve their productivity.

 

He explained that lack of effective social welfare was at the root of some incriminating actions that undermine the purpose of governance, noting that the commissioning of the newly built Permanent Secretaries Quarters marks a significant milestone in civil service welfare and institutional development.

 

“Insecurity begins when individuals are uncertain of what the next hour holds. This situation is especially challenging for family men and women, affecting confidence and decision-making,” he observed.

 

Fubara emphasized the need for proper maintenance of the facility and urged the beneficiaries to protect the project like a personal property, while directing the State Head of Service to appoint a facility manager to ensure long-term maintenance.

 

In her remarks, the Special Guest of Honour and Head of the Civil Service of the Federation, Mrs Didi Esther Walson-Jack, who unveiled the project, expressed appreciation to the governor and Rivers State for inviting her to commission the project.

 

She commended Fubara for prioritizing the welfare of Permanent Secretaries who are senior public servants and accounting officers, noting that the project reflects purposeful and visionary leadership, and urged other states to borrow a cue from the Rivers State Governor.

 

Walson-Jack described the initiative as a strategic investment in staff welfare and institutional continuity which she noted is in line with Renewed Hope Initiative on provision of mass housing and social stability.

 

“The commissioning of these houses reflect a deliberate commitment to the dignity, welfare, and productivity of senior public servants responsible for policy coordination and service delivery,” she said.

 

In his goodwill message, the National Secretary of the All Progressives Congress (APC), Senator Ajibode Bashiru, who led a high powered delegation on a visit to the governor, congratulated Rivers people for aligning with the Pan Nigerian political party, assuring that the interest of Rivers State will be duly protected in the APC.

 

He described President Bola Tinubu as a detribalised Nigerian who anchors his leadership on equity, fairness and justice, adding that the APC will provide a level playing ground for all.

 

The APC chief scribe also commended Fubara for providing good accommodation for public servants, stating that it will address issues of sabotage, compromise and disloyalty on the part of public servants.

 

Giving the project description,  Permanent Secretary, Rivers State Ministry of Works, Dr. Austin Ezekiel-Hart, said the estate comprises 29 units, including nine standalone duplexes and 20 terrace buildings.

 

Facilities feature a water treatment plant, synchronized power generators, CCTV and alarm systems, a gym, recreational areas, and green spaces—designed to enhance comfort, performance, and productivity.

 

Earlier, the Head of the Rivers State Civil Service, Dr Mrs Inyingi Brown, had thanked the governor for his visionary initiative and unwavering commitment to the welfare of Rivers State Civil Servants, and restated the commitment of the State civil servants to the success of Fubara’s administration.

 By: Taneh Beemene

 

 