Niger Delta
NDDC Attributes Office Project Delay To Covid-19
The Niger Delta Development Commission (NDDC), has attributed the delay on completion of its new headquarters to the Coronavirus (Covid-19) pandemic affecting many countries.
The commission said the global pandemic had delayed its importation into the country of materials and essential components needed for the project.
NDDC Acting Executive Director of Project, Dr Cairo Ojougboh, stated this in a statement yesterday in Port Harcourt by the commission’s Director of Corporate Affairs, Charles Odili.
According to him, the delay had affected the March 31 project completion date set by the Interim Management Committee (IMC) of the commission.
“The completion of the headquarters is no longer feasible because of the delay in importing materials already paid for due to Covid-19 pandemic.
“Based on the assessment of the situation, the contractor handling the project has affirmed that building would be handed over to us by April 30.
“We will hold the contractor liable to this deadline; just as we urge the contractor to continue not to let the commission down,” he said.
The executive director expressed satisfaction with the pace and quality of work on the new NDDC office complex.
The Project Consultant, Mr Ebiwene Bozimo was quoted in the statement to having assured the commission of delivering the project on or before April 30.
“So, while we await the importation of materials, every task that does not involve anything external is going on at the highest pace on site,” he said.
Niger Delta
INC, Others Partner PINL On Host Comm Dev. Advocacy
Niger Delta
Oborevwori Condoles Diri, Family, Bayelsans Over Passing Ewhrudjakpo’s Passing
Niger Delta
We Stalled Projects Inauguration To Honour Ewhrudjakpo – Ogbuku … As Oil Minster, PANDEF Eulogize Late D’Gov
-
News4 days agoRSIPA Outlines Plans To Boost Investors’ Confidence …China Applauds Fubara As Listening Gov
-
Niger Delta2 days ago
Oborevwori Condoles Diri, Family, Bayelsans Over Passing Ewhrudjakpo’s Passing
-
Politics2 days ago
Alleged Tax Law Changes Risk Eroding Public Trust — CISLAC
-
Politics2 days ago
DEFECTION: FUBARA HAS ENDED SPECULATIONS ABOUT POLITICAL FUTURE — NWOGU
-
Maritime2 days agoImo Category C Victory: NIMASA Staff Host Executive Management Party
-
Politics2 days ago
HILDA DOKUBO ASSUMES CHAIRMANSHIP, DENIES FACTIONS IN RIVERS LP
-
Rivers2 days ago
Group Urges LGA Chairmen To Prioritise Accountability, People-Centred Governance
-
Niger Delta2 days ago
We Stalled Projects Inauguration To Honour Ewhrudjakpo – Ogbuku … As Oil Minster, PANDEF Eulogize Late D’Gov