Return To Bodo-Bonny Road Project Site, FG Orders Julius Berger …Sets April 2024 New Deadline For Project’s Delivery

Published

on

The Minister of Works, Senator David Umahi, has ordered the contractor handling the 35-kilometer Bodo-Bonny road and bridge project in Rivers State, Julius Berger PLC, to return to the site and ensure its timely completion.
The minister emphasised the urgency and significance of the directive, noting that the project, initially awarded to Julius Berger Nigeria Plc by the previous administration at a revised cost of N199billion with a completion date of December 31, 2023, is crucial for economic transformation in the region, being approximately 84percent complete.
Umahi expressed bewilderment over the contractor’s absence from the site despite their commitment under the agreement to meet the revised completion date.
He set April 2024 as the new deadline for the project’s delivery.
Hosting a delegation from the Bodo–Bonny Road Peace Committee on Monday, December 5, 2023, Umahi assured the project’s host communities that the Federal Government, under President Asiwaju Bola Ahmed Tinubu’s Renewed Hope administration, is committed to ensuring the project’s swift completion.
As stated by his Chief Press Secretary (CPS), Uchenna Orji, the minister highlighted a partnership agreement in 2017 between the Federal Government through the Federal Ministry of Works and Nigeria LNG (NLNG) outlining the funding modalities for the project.
He faulted the contractor’s stance on project variations, highlighting that they had previously committed to completing the project without seeking additional variations, saying, “No equipment must be allowed to be moved out of site, they must complete that project as agreed and as signed and nothing has removed that responsibility which they willingly on their own signed.
“I implore you the Peace Committee to report to me the progress that has been made on that road.
“Bobo-Bonny project was augmented to 199billion, I am told by the Ministry and NLNG Limited that there was a document signed by Julius Berger that the project cannot be varied which means that the project cost cannot be increased, the project is about 35 kilometers”.
The minister, however, praised the host communities for maintaining peace with the contractor despite project delays while urging them to persist in their peaceful approach towards contractors working on projects in their vicinity.
He assured the delegation that the ministry would ensure the completion of the Bodo-Bonny road project by April 2024, saying, “Nobody will hold this country to ransom if they cannot do it, another person will come and do it and finish it even better but the only charge I give to you is not to allow any equipment out of sight until they complete the project”.
Umahi also assured that the Federal Government would manage a coastal road in the same region, facing even more significant site challenges, and the cost would be less than what the government is currently paying Julius Berger.
“I respect them for their quality and commitment, but we shouldn’t be taken for granted” “It is a character of arrogance for them to demobilize from site,” he added
Federal Director Bridges and Design, Engr. O. O. Awosanya, gave a brief history of the award and funding of the project by Julius Berger.
According to him, the initial date of completion of the project with 13 bridges was supposed to be December 31, 2023, saying, “We have three main bridges and we have nine mini bridges and one bridge over the pipeline.
“The project completion as of today is about 84percent and the contractor has requested for a review which is against the spirit of the propagated agreement that was signed between the Federal Government, the Nigerian Liquefied Natural Gas, and JB in 2021.”
Leader of the delegation and acting Chairman of the Peace Committee, Chief Charles John Jumbo, appreciated President Tinubu and the minister for the massive interventions and efforts they are bringing to the road sub-sector and changing the narrative of the road infrastructure in Nigeria.
He said the delegation was in the minister’s office to register their displeasure over the sudden demobilization from the site and abandonment of the Bodo-Bonny Road and Bridge project by Julius Berger Plc despite the huge funds committed by the Federal Government through NLNG.
Jumbo implored the timeouts intervention of Federal Government to avert the imminent hardship to be faced by the people of the area.

Featured

Fubara Frowns At Slow Pace Of Ndele–Omofo–Egmini–Agba-Ndele Road Project  ….Says Contract May Be Reviewed

Published

on

Rivers State Governor, Sir Siminalayi Fubara, has expressed dissatisfaction over the slow progress of work on the 14.5-kilometer Ndele/Omofo/Egamini/Agba-Ndele Road project located off the East–West Road in Emohua Local Government Area.

Addressing newsmen during an inspection tour of the project on Tuesday, the Governor noted that the pace and quality of work being delivered by the contracting firm, Messrs Stream Co. & Equipment Limited, fell below acceptable standards.

He was accompanied on the tour by the Permanent Secretary, Ministry of Works, Dr. Austin Ezekiel-Hart, who briefed the Governor on the status of the project and adjoining infrastructure.

Governor Fubara, who appeared visibly unsatisfied with what he saw on the stretch of the road, said his administration would not condone mediocrity or allow public funds to be wasted on underperforming projects. He, therefore, hinted that a review of the contract may be imminent to ensure the delivery of quality infrastructure to the people.

“I can say here already that the contractor handling the road from the bridge to the East–West Road is not doing a good job. I’m not happy about it. When I get back, there will be a need to review that contract because I’m not impressed. They don’t have the capacity, and we need capacity because we must have value for whatever money we’re spending,” the Governor said.

The Governor, however, commended Setraco Nigeria Limited for the standard and pace of work on the 240-meter Agba-Ndele/Abua Bridge, which forms a major component of the project. He explained that the bridge, which his administration inherited, would significantly improve connectivity among communities in the area once completed.

Governor Fubara stated that the bridge will serve as a key link between communities in Abua/Odual, Ahoada-East, and Emohua Local Government Areas, reducing travel time and providing an alternative route to the East–West Road.

He emphasised that the project demonstrates his administration’s commitment to rural connectivity and inter-community access, which are central to his development vision for Rivers State.

“Where we are standing on is a bridge connecting Abua/Odual, Ahoada-East, and Emohua Local Government Areas. The community that is connected to this bridge is Agba-Ndele.

“Instead of running through the East–West Road to Ahoada-East and heading into Port Harcourt or out of it, this bridge provides easy access for the Abua/Odual people to cross into Emohua, Agba-Ndele, and access the East–West Road in minutes,” he explained.

Governor Fubara also expressed optimism that the bridge would be ready for use in early 2026, noting that Setraco’s expertise and performance met his administration’s expectations for quality and delivery timelines.

He highlighted that projects of such importance should be handled by firms with the capacity to meet government standards.

The Governor further remarked that once completed, the bridge would serve as a crucial economic corridor for farmers and traders, especially those involved in agriculture and cultivation of local produce across the beneficiary local government areas.

He maintained that his administration is determined to deliver people-oriented projects that promote connectivity, strengthen commerce, and enhance livelihoods across the State.

“I’m really impressed with what I’ve seen on the bridge. I’m very sure that before the end of January, it might be completely ready for us to walk through and even drive across,” Governor Fubara said.

Reaffirming his vision for Rivers people, the Governor noted that his development plan seeks to integrate all parts of the State through strategic infrastructure investments that promote mobility, social cohesion, and economic growth.

He explained that his government is executing projects across multiple local government areas to ensure balanced development and inclusivity.

Governor Fubara stated that the administration will soon address the deplorable state of the Abua/Ahoada Road, which he said, will be included in the 2026 state budget.

“Our vision is to connect the entire Rivers State together, especially communities that have challenges of access. The bridge here connects Abua/Odual and Ahoada-East to Emohua and Port Harcourt. It will ease movement, promote trade, and boost our economy because agriculture is strong on this side. Moving goods to the city won’t be a problem anymore,” he said.

Governor Fubara reiterated his administration’s commitment to delivering quality infrastructure that provides value for public funds and meets the aspirations of Rivers people.

 

 

Continue Reading

Featured

Fubara Pledges Cleaner Gateway To PH City …Visits New Dumpsite At Igwuruta

Published

on

Rivers State Governor, Sir Siminalayi Fubara, has unveiled plans to permanently relocate the dumpsite along the busy Port Harcourt Airport–Obiri-Ikwerre Road, describing the current location as both a public health threat and a damaging first impression for visitors arriving in Port Harcourt, the State capital.

The Governor made this known on Tuesday during an inspection of a proposed replacement site, which is a disused burrow pit near Bambo Estate, off Eneka Road in Igwuruta, Ikwerre Local Government Area.

The location is being assessed as a potential permanent dumpsite for the State.

Governor Fubara, who was conducted by the Board  Chairman, Rivers State Waste Management Agency (RIWAMA), Dr Samuel Nwanosike, and its Managing Director, Dr Ibimina Wokoma, expressed concern about the environmental and health challenges posed by the existing site, which sits along a major entry point into the State.

“The kind of environmental hazards that we are facing there along the Airport–Obiri- Ikwerre Road; the smell on that road being the entrance into the State, we felt it’s not proper,” he said. “So, we are making alternative arrangements so we can have a permanent refuse dumpsite that meets acceptable standards.

“He added that the government would move swiftly to formalise ownership of the land and complete construction work on the access road to make the new site functional.“We have not concluded the issue of the burrow pit, but the access road, I think the government is doing something about it.

So, I will make sure that everything that needs to be done to ensure government owns this burrow pit is done,” he stated.

Governor Fubara also commended the Rivers State Waste Management Agency (RIWAMA) for what he described as a more assertive and improved approach to managing refuse across the State.In addition to the dumpsite inspection, the Governor also visited the Permanent Secretaries’ Quarters located in Elimgbu Town, Obio/Akpor Local Government Area, to assess the extent of ongoing construction work on the facility.

Continue Reading

Featured

Fubara Tasks New SSG On Honour, Service, Protection Of Rivers Interest 

Published

on

Rivers State Governor, Sir Siminalayi Fubara, has charged the newly appointed Secretary to the State Government (SSG), Barrister Benibo Anabraba, to uphold the dignity of his office, protect the interest of the State, and discharge his duties with honour, respect, and responsibility.

 

Governor Fubara gave the charge during the swearing-in ceremony of the new SSG, held on Monday at the Executive Council Chambers of Government House, Port Harcourt.

 

Describing Anabraba’s appointment as an act of divine favour, the Governor said positions of leadership are not attained by our own human effort but by God’s grace in our lives.

 

“Let me first congratulate you. I’m using the word ‘congratulations’ because a few of us, not by our power but by the special favour of God, find ourselves in exalted positions. It’s not because we are the best, but only by His grace.”

 

Governor Fubara noted that the Office of the Secretary to the State Government is one of great honour, occupied by only a few since the creation of Rivers State, and urged the new appointee to serve with humility and dedication.

 

He, however, expressed confidence in Anabraba’s capacity to deliver, citing his past record as a principal officer of the Rivers State House of Assembly.

 

“This position is a rare privilege. Guard that office with honour. Discharge your duties with respect. Protect the interest of Rivers State. When you leave office, let it be with honour, and that only comes through responsible service.

 

“I know you’re a dedicated person. This opportunity is not for show or display of power. It’s a call to duty,” he cautioned.

 

The Governor emphasised that the current administration is focused on restoring confidence of the people because peace has been achieved in the State.

 

He enjoined the new SSG to align with the vision of the administration and contribute meaningfully to the collective progress of Rivers people.

 

“We are emerging from a very difficult period and must reassure our people that we mean well for them, especially now that peace has returned to Rivers State. By the grace of God, do your work well. Help us succeed in this assignment that God has given to us,” the Governor added.

 

 

 

Continue Reading

Trending