Business
LAMATA Explains Slow Work On Lagos Rail Project
The Lagos Metropolitan Area Transport Authority (LAMATA), said on Tuesday, that Right of Way (RoW) recovery and the relocation of services were responsible for the slow pace of work on the Light Rail Project, on the ongoing Lagos-Badagry Expressway project.
LAMATA’s Head of Media and Communications, Mr Kolawole Ojelabi, told newsmen in Lagos that the project was stopped for almost three years because of various problems of obstruction on the RoW.
“We have given different completion dates for the project but one of the challenges that we had was that the train was originally to go to the Iddo Railway Terminus but the Railway Act did not allow us to do such.
“Since we could not take the train station to Iddo, we had to change the alignment, and in changing that, there were a lot of obstructions on the way.
“For instance, there is a fertiliser plant around Ijora belonging to the Federal Government, we had to negotiate to use their compound, so that we could take away their warehouse. We had to build another warehouse for them.
“Around Ijora too, there was a mosque that we had to demolish and build another one.
“Then moving into the lagoon, there were two major challenges, there was the relocation of gas link, a gas pipe underneath the lagoon, which also took some time.
“We also discovered that there was the wreckage of a ship that was at the bottom of the lagoon, that also had to be removed. These delayed the time line for the delivery of the project.
“From the initial plan of the Lagos State Government, this train ought to have been delivered in 2012 or 2013,’’ he said.
Ojelabi explained that LAMATA lost about three years to the recovery of RoW, adding that, the state government had to bear the additional costs, which were not in the initial budget.
This, according to him was to ensure that the structures were solid because rail infrastructure is expected to last a minimum of 100 years.
He said that the blue rail line project was a 27-kilometre project which runs from Okokomaiko to the Marina and is expected to have 13 train stations and the trains are targeted to lift a minimum of 400,000 passengers daily, when completed.
Ojelabi explained that the project was divided into three phases, with each phase further divided into three segments.
“The first phase of the project is 95 per cent completed, that is from Mile 2 to the National Theatre.
“The second phase which is from National Theatre to Marina is about 45 per cent completed and massive work is going on there now.
“By the time all the piers are built, particularly those in the lagoon, that is, the superstructure, the project would no longer take time to complete,’’ he said.
Ojelabi said that the scope of work done in phase one included the station buildings and rail tracks, adding that, installation of electricity and communication gadgets were being expected, to make the section functional.
He explained that there were supposed to be a total of 13 train stations out of which four have been completed and two others are under construction.
Ojelabi said that, there was a design in the project for the National Theatre to be a major terminus under the Bus Reform Programme of the government, where vehicles would take passengers disembarking from the train to various parts of the state.
He commended late Mrs Oluremi Oyo, former Managing Director of the News Agency of Nigeria (NAN), for the role she played in speeding up the completion of the train station at the National Theatre in Iganmu, some years back.
The media head explained that Oyo gave up a portion of land that led to the shifting of the fence of NAN to allow construction of a major pier.
Business
Customs Launches Digital Vehicle Verification System To Tackle Smuggling
Business
NDDC Unveils Naval Facilities To Boost Region’s Security
Business
FG Fixes Uniform Prices for Housing Units Nationwide, Approves N12.5m For 3-bedroom Bungalow ……..Says Move To Enhance Affordability, Ensures Fairness
“The approved selling prices are as follows: One-bedroom semi-detached bungalow, N8.5 million; two-bedroom semi-detached bungalow: N11.5 million and three-bedroom semi-detached bungalow, N12.5 million,” the statement added.
Minister of Housing and Urban Development, Ahmed Dangiwa, stated that priority in the allocation of the housing units would be given to low and middle-income earners, civil servants at all levels of government, employees in the organised private sector with verifiable sources of income, and Nigerians in the Diaspora who wish to own homes in the country.
The Permanent Secretary in the ministry, Dr. Shuaib Belgore, explained that several payment options have been provided to make the houses affordable and flexible. These include outright (full) payment, mortgage, rent-to-own scheme, and installment payment plans.
The ministry further announced that the sale of the completed housing units across the northern and southern regions will soon commence.
“Applications can be made through the Renewed Hope Housing online portal at www.renewedhopehomes.fmhud.
The ministry, however, clarified that the approved prices apply strictly to the Renewed Hope Housing Estates which are funded through the ministry’s budgetary allocation, as against the Renewed Hope Cities in Karsana Abuja, Janguza Kano, Ibeju Lekki, Lagos which are being funded through a Public Private Partnership (PPP).
