Connect with us

Oil & Energy

Egbin’ll Function To Installed Capacity After Repairs – CEO

Published

on

The Chief Executive Officer
of Egbin Thermal Plant, Mr Mike Uzoigwe,  says the repairs of its sixth turbine unit (ST-06), will add 220 Megawatts (MW) to the national grid.
Uzoigwe said this when he inspected the ongoing repairs of the turbine in Lagos recently.
According to him, the plant may have waved over, its installed capacity generation challenges barely seven years down the line.
He said the power plant, which had an installed capacity of 1,320 MW, had suffered setback for some years due to ageing parts and paucity of funds to upgrade the facility.
The Tide source, however, reports that the plant was generating about 700 MW before it experienced a system collapse.
Uzoigwe, who confirmed the system collapse, added that power would be restored in a short while due to its new black-starting mechanism.
“Before now, system collapse takes power plants in Nigeria about five days to restore electricity, but the black-starting technology would make it possible within hours.’’
Uzoigwe, who conducted journalists round the plant, expressed joy that the plant would be operating at full capacity after about seven years of partial operation.
He said the plant was constructed about 30-years ago to operate on six turbine units at 220 MW each, until 2006 when the sixth unit exploded due to some water tube challenges.
The chief executive officer said the contract for repair was awarded to the Original Equipment Manufacturer, Hitachi of Japan.
According to him, the company has spent so much money to secure some parts of the plant.
He said between 2011 and 2012, it ordered and replaced all the cannibalised spares and also awarded contract for the final repairs at approximately N1 billion.
“Unit six job will last for 90 days after which the unit should be handed over completely repaired and ready for operation.
“Work effectively started on July 1, 2013, and still going on. This will lay to rest the rumours that money meant for ST-06 repairs was diverted some times in the past,” he said.
He explained that the delay in commencing the job was because it did not get the nod of the Bureau for Public Procurement (BPP) early enough to award the contract.
This, he explained, was due to BPP’s exhaustive procedure of making sure the contract price was right.
“We have started anyway and it is hoped we will deliver on time. We are in the interim discovering everyday some other parts we need to replace.
“This will cost some more money and we will soon take it up with the Minister of Power to source for more funds,” he said.
Uzoigwe welcomed the privatisation exercise, adding that although the takeover of the assets would soon happen.
According to him, the management has a philosophy of continuation with all what it is suppose to be doing until the day the new investors takeover.
Reports say that works were ongoing at the plant as experts handling different parts of the turbine were seen laying some of the new parts strategically around the affected turbine.
Uzoigwe, who gave estimates of parts of the plant, accordingly, said repair of damaged boiler was awarded to KEPCO at 17.95 million dollars which was almost 100 per cent completed.
According to him, the dry storage part was awarded to Igodi at N9.8 million, while the emergency repairs of generator rotor and BFP motor rotors were awarded to Maurubeni at 6.79 million dollars.
He said the total replacement of the damaged reheater outlet coils and comprehensive inspection of reheater inlet coils were awarded to KEPCO at 4.94 million dollars and N74. 61 million, respectively.
He added that the supply of new AVR cubicle for thyristor excitation system was awarded to Marubeni at 117.9 million Yen, while the repair of LP turbine rotor journals was awarded to G.E at 1.52 million dollars.
According to Uzoigwe, all the listed parts are almost 100 per cent completed, except for the supply of cannibalised items which are at 80 per cent completion.

Continue Reading

Oil & Energy

FG Explains Sulphur Content Review In Diesel Production 

Published

on

The Federal Government has offered explanation with regard to recent changes to fuel sulphur content standards for diesel.
The Government said the change was part of a regional harmonisation effort, not a relaxation of regulations for local refineries.
The Chief Executive, Nigerian Midstream and Downstream Petroleum Regulatory Authority (NMDPRA), Farouk Ahmed, told newsmen that the move was only adhering to a 2020 decision by the Economic Community of West African States (ECOWAS) which mandated a gradual shift to cleaner fuels across the region.
Ahmed said the new limits comply with the decision by ECOWAS that mandated stricter fuel specifications, with enforcement starting in January 2021 for non-ECOWAS imports and January 2025 for ECOWAS refineries.
“We are merely implementing the ECOWAS decision adopted in 2020. So, a local refinery with a 650 ppm sulphur in its product is permissible and safe under the ECOWAS rule until January next year where a uniform standard would apply to both the locally refined and imported products outside West Africa”, Ahmed said.
He said importers were notified of the progressive reduction in allowable sulphur content, reaching 200 ppm this month from 300 ppm in February, well before the giant Dangote refinery began supplying diesel.
Recall that an S&P Global report, last week, noted a significant shift in the West African fuel market after Nigeria altered its maximum diesel sulphur content from 200 parts per million (ppm) to around 650 ppm, sparking concerns it might be lowering its standards to accommodate domestically produced diesel which exceeds the 200 ppm cap.
High sulphur content in fuels can damage engines and contribute to air pollution. Nevertheless, the ECOWAS rule currently allows locally produced fuel to have a higher sulphur content until January 2025.
At that point, a uniform standard of below 5 ppm will apply to both domestic refining and imports from outside West Africa.
Importers were previously permitted to bring in diesel with a sulphur content between 1,500 ppm and 3,000 ppm.
It would be noted that the shift to cleaner fuels aligns with global environmental efforts and ensures a level playing field for regional refiners.

Continue Reading

Oil & Energy

PHED Implements April 2024 Supplementary Order To MYTO

Published

on

The Port Harcourt Electricity Distribution (PHED) plc says it has commenced implementation of the April 2024 Supplementary Order to the MYTO in its franchise area while assuring customers of improved service delivery.
The Supplementary order, which took effect on April 3, 2024, emphasizes provisions of the MYTO applicable to customers on the Band A segment taking into consideration other favorable obligations by the service provider to Band A customers.
The Head, Corporate Communications of the company, Olubukola Ilvebare, revealed that under the new tariff regime, customers on Band A Feeders who typically receive a minimum supply of power for 20hours per day, would now be obliged to pay N225/kwh.
“According to the Order, this new tariff is modeled to cushion the effects of recent shifts in key economic indices such as inflation rates, foreign exchange rates, gas prices, as well as enable improved delivery of other responsibilities across the value chain which impact operational efficiencies and ability to reliably supply power to esteemed customers.
“PHED assures Band A customers of full compliance with the objectives of the new tariff order”, he stated.
Ilvebare also said the management team was committed to delivering of optimal and quality services in this cost reflective dispensation.
The PHED further informed its esteemed customers on the other service Bands of B, C D & E, that their tariff remains unchanged, adding that the recently implemented supplementary order was only APPLICABLE to customers on Band A Feeders.

Continue Reading

Oil & Energy

PH Refinery: NNPCL Signs Agreement For 100,000bpd-Capacity Facility Construction 

Published

on

The Nigerian National Petroleum Company Ltd (NNPCL) has announced the signing of an agreement with African Refinery for a share subscription agreement with Port-Harcourt Refinery.
The agreement would see the co-location of a 100,000bpd refinery within the Port-Harcourt Refinery complex.
This was disclosed in a press statement on the company’s official X handle detailing the nitty-gritty of the deal.
According to the NNPCL, the new refinery, when operational, would produce PMS, AGO, ATK, LPG for both the local and international markets.
It stated, “NNPC Limited’s moves to boost local refining capacity witnessed a boost today with the signing of share subscription agreement between NNPC Limited and African Refinery Port Harcourt Limited for the co-location of a 100,000bpd capacity refinery within the PHRC complex.
“The signing of the agreement is a significant step towards setting in motion the process of building a new refinery which, when fully operational, will supply PMS, AGO, ATK, LPG, and other petroleum products to the local and international markets and provide employment opportunities for Nigerians.

By: Lady Godknows Ogbulu

Continue Reading

Trending