Business
LAMATA Explains Slow Work On Lagos Rail Project
The Lagos Metropolitan Area Transport Authority (LAMATA), said on Tuesday, that Right of Way (RoW) recovery and the relocation of services were responsible for the slow pace of work on the Light Rail Project, on the ongoing Lagos-Badagry Expressway project.
LAMATA’s Head of Media and Communications, Mr Kolawole Ojelabi, told newsmen in Lagos that the project was stopped for almost three years because of various problems of obstruction on the RoW.
“We have given different completion dates for the project but one of the challenges that we had was that the train was originally to go to the Iddo Railway Terminus but the Railway Act did not allow us to do such.
“Since we could not take the train station to Iddo, we had to change the alignment, and in changing that, there were a lot of obstructions on the way.
“For instance, there is a fertiliser plant around Ijora belonging to the Federal Government, we had to negotiate to use their compound, so that we could take away their warehouse. We had to build another warehouse for them.
“Around Ijora too, there was a mosque that we had to demolish and build another one.
“Then moving into the lagoon, there were two major challenges, there was the relocation of gas link, a gas pipe underneath the lagoon, which also took some time.
“We also discovered that there was the wreckage of a ship that was at the bottom of the lagoon, that also had to be removed. These delayed the time line for the delivery of the project.
“From the initial plan of the Lagos State Government, this train ought to have been delivered in 2012 or 2013,’’ he said.
Ojelabi explained that LAMATA lost about three years to the recovery of RoW, adding that, the state government had to bear the additional costs, which were not in the initial budget.
This, according to him was to ensure that the structures were solid because rail infrastructure is expected to last a minimum of 100 years.
He said that the blue rail line project was a 27-kilometre project which runs from Okokomaiko to the Marina and is expected to have 13 train stations and the trains are targeted to lift a minimum of 400,000 passengers daily, when completed.
Ojelabi explained that the project was divided into three phases, with each phase further divided into three segments.
“The first phase of the project is 95 per cent completed, that is from Mile 2 to the National Theatre.
“The second phase which is from National Theatre to Marina is about 45 per cent completed and massive work is going on there now.
“By the time all the piers are built, particularly those in the lagoon, that is, the superstructure, the project would no longer take time to complete,’’ he said.
Ojelabi said that the scope of work done in phase one included the station buildings and rail tracks, adding that, installation of electricity and communication gadgets were being expected, to make the section functional.
He explained that there were supposed to be a total of 13 train stations out of which four have been completed and two others are under construction.
Ojelabi said that, there was a design in the project for the National Theatre to be a major terminus under the Bus Reform Programme of the government, where vehicles would take passengers disembarking from the train to various parts of the state.
He commended late Mrs Oluremi Oyo, former Managing Director of the News Agency of Nigeria (NAN), for the role she played in speeding up the completion of the train station at the National Theatre in Iganmu, some years back.
The media head explained that Oyo gave up a portion of land that led to the shifting of the fence of NAN to allow construction of a major pier.
Business
Kenyan Runners Dominate Berlin Marathons
Kenya made it a clean sweep at the Berlin Marathon with Sabastian Sawe winning the men’s race and Rosemary Wanjiru triumphing in the women’s.
Sawe finished in two hours, two minutes and 16 seconds to make it three wins in his first three marathons.
The 30-year-old, who was victorious at this year’s London Marathon, set a sizzling pace as he left the field behind and ran much of the race surrounded only by his pacesetters.
Japan’s Akasaki Akira came second after a powerful latter half of the race, finishing almost four minutes behind Sawe, while Ethiopia’s Chimdessa Debele followed in third.
“I did my best and I am happy for this performance,” said Sawe.
“I am so happy for this year. I felt well but you cannot change the weather. Next year will be better.”
Sawe had Kelvin Kiptum’s 2023 world record of 2:00:35 in his sights when he reached halfway in 1:00:12, but faded towards the end.
In the women’s race, Wanjiru sped away from the lead pack after 25 kilometers before finishing in 2:21:05.
Ethiopia’s Dera Dida followed three seconds behind Wanjiru, with Azmera Gebru, also of Ethiopia, coming third in 2:21:29.
Wanjiru’s time was 12 minutes slower than compatriot Ruth Chepng’etich’s world record of 2:09:56, which she set in Chicago in 2024.
Business
NIS Ends Decentralised Passport Production After 62 Years
Business
FG To Roll Out Digital Public Infrastructure, Data Exchange, Next Year
-
Sports4 days ago
CAFCL : Rivers United Arrives DR Congo
-
Sports4 days ago
FIFA rankings: S’Eagles drop Position, remain sixth in Africa
-
Sports4 days ago
NPFL club name Iorfa new GM
-
Sports4 days ago
NNL abolishes playoffs for NPFL promotion
-
Sports4 days ago
NSF: Early preparations begin for 2026 National Sports Festival
-
Sports4 days ago
Kwara Hopeful To Host Confed Cup in Ilorin
-
Sports4 days ago
RSG Award Renovation Work At Yakubu Gowon Stadium
-
Politics4 days ago
Rivers Assembly Resumes Sitting After Six-Month Suspension