DisCos Ignore 2,495.3MW In One Week – Report
Electricity distribution companies in Nigeria did not utilise a total of 2,495.3 megawatts of electricity in one week this month. This is in spite of apparent high demand for electricity nationwide.
This is contained in the Transmission Company of Nigeria’s latest report on national grid performance: TCN-Discos Interface from April 2 to April 8, 2022.
The report revealed that some Discos failed to utilise over 2,400MW of electricity during the period despite the fact that they were nominated for the electricity load.
Although the report indicated that some Discos took and distributed excess load than they nominated for during the week under review, it was observed that others failed to distribute a huge quantum of electricity daily, amidst the low supply across the country.
It showed the maximum load nomination by each Disco, their approved Multi-Year Tariff Order allocation, their actual consumption, the quantum of unutilised load by some of them, as well as the excess load taken by others.
Nigeria’s 11 Discos, which include Abuja, Benin, Eko, Enugu, Ibadan, Ikeja, Jos, Kaduna, Kano, Port Harcourt and Yola, have attracted series of complaints about the poor delivery of electricity by the firms.
It was observed that on April 2, for instance, a total of 373.97MW of power was unutilised by five power distribution companies, as Eko did not utilise 118.29MW; Ibadan, 169.77MW; Ikeja, 63.19MW; Kano, 13.18MW; and Port Harcourt, 9.54MW.
On April 3, six power distributors failed to utilise 189.84MW. They include Eko, 26.99MW; Enugu, 1.65MW; Ibadan, 44.85MW; Ikeja, 51.66MW; Kano, 48.35MW and Port Harcourt, 16.34MW.
The number of Discos with unutilised electricity load increased to eight on April 4, as a total of 309.2MW was not distributed to customers across the country by the power firms.
Eko Disco did not utilise 27.10MW; Enugu, 78.18MW; Ibadan, 60.39MW; Ikeja, 46.03MW; Jos, 23.74MW; Kaduna, 5.35MW; Kano, 50.28MW; and Port Harcourt, 18.13MW.
The TCN report obtained by The Tide’s source in Abuja further showed that on April 5, seven Discos failed to utilise 238.44MW of electricity and they include Eko, 44.49MW; Enugu, 20.05MW; Ibadan, 35.11MW; Ikeja, 67.39MW; Jos, 4.12MW; Kaduna, 9.86MW; and Kano, 57.22MW.
The highest quantum of unutilised power during the review week was recorded on April 6, as seven power distributors failed to utilise nor distributed 596.07MW of electricity to consumers.
Benin Disco did not utilise 40.42MW; Eko, 200.59MW; Enugu, 66.58MW; Ibadan, 46.54MW; Ikeja, 199.05MW; Jos, 19.50MW; and Kano, 23.39MW.
It was also observed that on April 7, seven Discos could not utilise 424.63MW. The Discos include Benin, 4.58MW; Eko, 127.86MW; Enugu, 69.65MW; Ibadan, 39.95MW; Ikeja, 114.12MW; Jos, 30.04MW; and Kano, 42.43MW.
The report further showed that on April 8, six Discos failed to utilise 363.15MW of electricity, as the unutilised load of Benin Disco was 42.91MW; Eko, 86.97MW; Enugu, 30.94MW; Ibadan, 112.12MW; Ikeja, 89.28MW; and Kano, 0.93MW.
Power supply in Nigeria had been poor over the years but grew worse in the past weeks following the collapse of the national electricity grid, which occurred about four times within the space of one month.
Despite the series of grid collapse, the latest report on the grid performance from TCN revealed that the power situation might have been further worsened by the over 2,400MW of electricity that was not utilised by Discos within one week.
Business
SMEs Dev: Firms Launch N100m Loan Scheme
The facility will be disbursed through participating Microfinance Institutions (MFIs), which will in turn extend the loans to their customers, particularly SMEs, as they directly interface with businesses at the grassroots level.
The Executive Director of COMCIN, Mr. Micheal Ogbaa who represented the Chairman, Dr. Iredele Oyedele (FCA, FCCA), said the initiative is designed to strengthen micro-lending institutions and expand access to finance for grassroots entrepreneurs, particularly women and youths in the informal sector.
Ogbaa explained that COMCIN does not lend directly to individuals but works through its network of microfinance and cooperative institutions, which in turn provide loans to end users.
“We came together to advocate for the microfinance ecosystem. Commercial banks often exclude people at the grassroots, but our members are positioned to reach them. This facility will empower them to do more,” he said.
He noted that the loan scheme offers low interest rates and flexible repayment plans, making it more accessible to small business owners.
According to him, about 90 percent of beneficiaries are expected to be women, who play a key role in sustaining families and driving economic activities at the local level.
“Our focus is on traders, service providers, and players in the informal sector. These are the real movers of the economy. By supporting them, we are strengthening families and contributing to national development,” he added.
Ogbaa disclosed that eligible SMEs with proven integrity and business track records could access up to N5 million each through participating micro-lending institutions. The rollout has commenced in Lagos and will extend to Abuja, Enugu, and other regions, including the South-West, South-East, and North-East.
He said 12 micro-lending institutions have already benefited from the scheme, while 85 applications are currently being processed under the pilot phase.
“Our target is to reach at least 100,000 SMEs nationwide. We are building a platform that connects funding partners with credible micro-lending institutions, creating a reliable channel for financial inclusion,” Ogbaa said.
He added that COMCIN is also working to attract larger funding pools from development finance institutions and private investors, noting that successful implementation of the pilot phase would boost confidence and unlock more capital for SMEs.
“We have seen encouraging testimonies from early beneficiaries. As we demonstrate transparency and efficiency, more institutions will be willing to channel funds through us,” he said.
Business
Yenagoa’s Radisson Hotel Ready December — NCDMB, Other
Business
RIRS Sets Tomorrow As Deadline For Individual Tax Returns Filing
-
Opinion15 hours ago
Ozoro Festival: Tradition or Tyranny?
-
News1 day agoRSG Reiterates Commitment To Youth Dev
-
Oil & Energy1 day agoTranscorp Energy, Renewvia Partner On Renewable Energy Gap
-
Business1 day agoNSCDC Discloses Illegal Dump Site In Ikwerre Community
-
Rivers1 day agoPolice Launch Community-Centred National Day Celebration In Rivers, Today
-
Business1 day agoYenagoa’s Radisson Hotel Ready December — NCDMB, Other
-
Politics15 hours ago
RIVERS WOMEN RALLY SUPPORT, CONTINUOUS PRAYERS FOR TINUBU
-
Maritime1 day agoMWUN Raises Alarm Over Port Security Lapses In Lagos