Connect with us

Oil & Energy

Total, French Embassy Initiate Scholarship Programme

Published

on

A joint scholarship scheme by Total Exploration and Production Nigeria Limited (TEPNG) and the Embassy of Franch in Nigeria have been initiated to promote educational development in Nigeria.

The scheme called TEPNG/Quaid’orsay, TQJ would have the duo invest up to 270,000 Euros or about N56 million annually.

Under the scheme, five Nigerians are to benefit from a yearly scholarship sponsored by Total and the French Embassy in Nigeria with effect from the 2012/2013 academic year at the cost of 54,000 Euro each.

According to a statement by the Company’s Manager External Communication, Charles Ebereonwu, the agreement to formalize the scheme was signed at the French Embassy in Abuja between TEPNG and the Embassy.

The statement stated that TEPNG’s Managing Director/Chief Executive, Mr Guy Maurice signed for TEPNG while the Ambassador of France, Mr Jacques Champagne de Labriolle signed for the Embassy.

It also disclosed that the programme started with a pilot scheme this year when a candidate was selected to and sponsored to study International Law in France. The agreement makes provision for a four-man steering committee to manage the scheme on behalf of the parties.

Benefits to be enjoyed by the selected beneficiaries, the statement stated include a sum to cover travel expenses, academic fees if in a private university or institution in France, living expenses for 10 months with feeding, housing costs, and academic text or materials inclusive.

Others are logistics support in obtaining necessary permits or visas for selected students, health insurance for each beneficiary (bourse de Couverture Sociale) such as will give the beneficiaries the status of French government scholarship’s beneficiaries and the health care benefits associated with this status; and 60 hours minimum language  training in Nigeria for the selected students and school fees for beneficiaries selected into public universities in France.

Commenting on the programme, Ambassador Champagne de Labriolle said that the programme was borne out of the need to contribute to the training of Nigerians in different fields of endeavour.

“Understanding changes in your environment is not a matter of specialization but a matter of personal balance and culture, the French Ambassador noted and lauded TEPNG for its contributions to the development of the Nigerian Society.

Also speaking TEPNG’s MD pointed out that such initiative on the part of the company was a reflection of its confidence in the country and a continuation of what it has been doing in the past.

The Quai d’Orsay educational cooperation between Total and the French Embassy started in 2011 and already operates in other subsidiaries.

Total’s delegation to the event were the Executive General Manager, Corporate Services, Mr Vincent Nnadi, Executive General Manager, Public Affairs and Communication, Mr Chidi Momah, Training  and Development Manager, Mr Sam Nkwo and Senior Legal Counsel, Mr Adesina Salawu.

The Embassy’s team included the Counsellor for Co-operation and Culture, Mr Patrick Perez. Total has been collaborating with top rated institutions around the world as part of its contribution towards human capacity development in its host communities.

It is the main sponsor of the Institute of Petroleum Studies (IPS), a postgraduate institution at the University of Port Harcourt which it runs with the Prestigious Institute France du Patrole (IFP) France.

Continue Reading

Oil & Energy

15-Year Blackout: NDPHC Begins Electricity Project In Kaduna Community 

Published

on

The Niger Delta Power Holding Company Limited (NDPHC) has commenced a major electricity project aimed at ending a 15-year blackout in Rigasa community, Igabi Local Government Area of Kaduna State.
The General Manager, Corporate Communication and External Relations, NDPHC, Nazo Agim, made this known in a statement, in Abuja, at the weekend.
Agim said that the project, facilitated by the Bola Ahmed Tinubu Ideological Group (BAT-IG), comprises a two-kilometre 11kV line, a 1.5-kilometre 33kV line and a 7.5MVA, 33/11kV injection substation.Access Services
According to him, the project is designed to strengthen electricity distribution and improve power supply to residents and businesses in the community.
He said that the Rigasa project underscored NDPHC’s commitment to extending critical electricity infrastructure beyond generation to bridge distribution gaps.
He also said that the project would stimulate socioeconomic development and improve the quality of life in underserved communities across Nigeria.
Agim disclosed that a groundbreaking ceremony was performed earlier on Friday, by the Kaduna state Deputy Governor, Dr. Hadiza Balarabe, who represented Governor Uba Sani.
According to him, Balarabe, while speaking during the ceremony commended NDPHC for the intervention, describing it as a life-saving initiative that would address the community’s longstanding electricity challenges.
The NDPHC Managing Director, Jennifer Adighije, reaffirmed the company’s commitment to addressing the community’s electricity challenges.
Represented by the Executive Director, Networks, Babayo Bello, Adighije also reiterated NDPHC’s commitment to supporting President Bola Tinubu’s vision of improving electricity supply across the country.
She said that although NDPHC’s primary mandate was power generation, the company’s interventions also extended to transmission and distribution infrastructure to address critical gaps and expand electricity access.
According to her, the Rigasa project represents a worthwhile investment that will ease residents’ hardship and demonstrate the impact of targeted infrastructure development in underserved communities.Access Services
NDPHC Executive Director, Strategy and Commercial, Patrick Obahiagbon, commended the Kaduna state government and the community for their cooperation and support for the project.
The District Head of Rigasa, Mohammed Idris, also commended NDPHC’s management for its commitment to expanding electricity access in the community.
Continue Reading

Oil & Energy

FG Commissions 640MW Transmission Capacity To National Grid

Published

on

As the federal government intensifies efforts to strengthen Nigeria’s power infrastructure, it has commissioned 640 megawatts (MW) of electricity transmission capacity to the national grid with an additional six transmission substations in Kano and Katsina states, respectively.
The projects comprise four substations at Walalambe, Kumbotso, Dakata and Dan-Agundi in Kano State, which collectively add 544MW of transmission capacity, and two 60 megavolt amperes (MVA) substations in Kankia Local Government Area of Katsina State, contributing another 96MW.
The additional capacity is expected to improve the transmission network’s ability to evacuate and deliver available electricity to distribution companies and consumers in the two states.
The Ministry of Power announced the developments in a statement issued at the weekend.
According to the statement, the additional capacity is expected to improve the transmission network’s ability to evacuate and deliver available electricity to distribution companies and consumers in the two states.
The projects, however, increase transmission capacity rather than electricity generation, implying that their impact on supply would depend partly on the availability of power from generating plants and the capacity of downstream distribution networks.
Speaking at the commissioning of the Kankia substation, the Minister of Power, Joseph Tegbe, said the projects reflected President Bola Tinubu’s commitment to improving the country’s electricity infrastructure.
“Mr. President’s Renewed Hope Agenda recognizes that economic ambition requires dependable infrastructure,” Tegbe said.
He added that investments in electricity infrastructure would strengthen the foundations for business expansion, employment and economic growth.
The Kankia substations comprise two 60 MVA, 132/33 kilovolt (kV) facilities designed to strengthen the transmission network serving Katsina State and neighbouring areas.
Tegbe said the infrastructure would improve the network’s ability to distribute available electricity, supporting commercial activities and household welfare.
He also urged residents to protect the facilities against vandalism and other activities that could disrupt electricity infrastructure, asking them to report suspicious activities to TCN or security agencies.
Katsina State Governor, Dikko Umaru Radda, described the project as a significant investment in the state’s electricity infrastructure.
Radda stated that improved electricity supply could support industrial development, economic growth and public service delivery.
He further commended the President, the Federal Ministry of Power and TCN for completing the project.
It would be noted that the latest projects come amid a broader government’s drive to address bottlenecks in Nigeria’s electricity transmission network, which has constrained the amount of electricity that can be delivered to distribution companies and end users.
Continue Reading

Oil & Energy

NBTI Unveils $600m Investment Pipeline Innovation

Published

on

The National Board for Technology Incubation (NBTI) has unveiled an investment and development-finance pipeline exceeding $600 million, alongside a proposed solar energy programme targeting one million micro and small businesses across Nigeria.
The Director-General, NBTI, Dr Kazeem Raji, disclosed this while presenting the outcomes of the 2026 NextGen Innovation Challenge at a World Press Conference, Abuja.
Raji said the investment pipeline comprised a proposed $500m solar energy programme for universities and polytechnics, which would be developed in partnership with Gigawatt Global, and a $100m financing opportunity linked to the Tinubu Light Initiative under a memorandum of understanding with Financial Innovation for Impact, UK, also known as Cambridge Investors.
He, however, clarified that the funds had not been fully secured or disbursed, stressing that their realisation would depend on due diligence, financing arrangements, contractual commitments, regulatory approvals and implementation requirements.
“These figures represent proposed investment and financing opportunities and should not be interpreted as $600m already received, disbursed or fully deployed in Nigeria,” he said.
According to Raji, the initiative was designed to connect Nigerian innovators with international investors, business leaders and development partners to accelerate the commercialisation of indigenous technologies.
He said the challenge attracted 298 Nigerian innovators from all 36 states and the Federal Capital Territory, up from 105 participants in 2025.
The innovations showcased covered artificial intelligence, robotics, agriculture, healthcare, education, renewable energy, telecommunications, digital technology, enterprise software, 3D printing and advanced manufacturing.
“Our message is straightforward: Nigeria’s innovators deserve visibility, our enterprises deserve opportunities to grow, and our technologies deserve pathways to the marketplace,” Raji said.
He added that NBTI’s priority was to move beyond showcasing ideas to helping innovators develop commercially viable products, establish sustainable businesses and create jobs.
The proposed Tinubu Light Initiative is expected to support one million micro and small businesses through access to solar energy solutions, with a proposed target of training and deploying 10,000 field marketers and creating 50,000 direct youth employment opportunities.
The initiative also targets N30bn in blended financing for its first phase and estimates annual economic benefits of about N12bn, subject to its underlying assumptions and implementation outcomes.
Raji said the programme was conceived to address the energy challenges facing small businesses, including high operating costs associated with unreliable electricity and dependence on petrol and diesel generators.
Tailors, barbers, hairdressers, pharmacies, food vendors, neighbourhood retailers, printing businesses and digital-service providers, he stated, are among the potential beneficiaries.
He said the initiative also envisaged opportunities to promote business formalisation and financial inclusion, particularly among informal enterprises, where appropriate arrangements could be established.
However, the NBTI director-general acknowledged that the programme’s success would depend on sound financing, transparent beneficiary selection, reliable equipment, maintenance arrangements and measurable delivery.
“Our vision is to make clean-energy access an enabler of enterprise development, not merely an infrastructure intervention,” he said.
Continue Reading