The contractor handling the construction of the arrival terminal building at the Port Harcourt International Airport, Omagwa, the Inter-Bau Construction Limited, says it is working hard to meet the 60-day deadline given to it by the Federal Government to bring the job to an appreciable level.
The company has also promised to complete the job on or before the end of this year, all things being equal.
The Project Supervisor, also the Deputy Site Manager of the company, Engr Moses Nweke, who disclosed this while speaking to aviation correspondents at the Port Harcourt International Airport, said they are working towards roofing the building before the expiration of the 60-day ultimatum.
Nweke noted that there had been a lot of challenges in the course of executing the contract, but indicated that the challenges are being addressed, especially in the area of rainfall, which has affected their operations.
“The Acting President, Prof. Yemi Osinbajo gave us 60 days on his last visit to Port Harcourt to bring the project to an appreciable level.
“We are determined to do that, and one of the ways to tackle that is that we will roof the place, and as soon as roofing is done, we can be under the roof to do other jobs.
“Rain has been one of our major challenges, but int we are putting things together to ensure that work progresses, as you can see that the work is 40 per cent done holistically and the block work has also started,” Nweke stated.
On the relationship with the airport management and workers, the supervisor said that there is cordial relationship with the management and workers, adding that the deadline given by the acting president has started counting since July 28th, 2017.