Rivers
Julius Berger reiterates commitment to Bodo- Bonny Road Project
Julius Berger Nigeria Plc has reaffirmed its steadfastness in its mission to delivering transformative infrastructure projects that align with Nigeria’s developmental priorities.
In a statement issued by the leading construction firm and signed by its Head, Corporate Communications, Mr. Emeiseifa James Agama, Julius Berger noted that, “For over 50 years, we have partnered with the Federal Government, communities, and stakeholders to deliver transformative infrastructure solutions with professionalism, transparency, and adherence to the highest standards”.
“The Bodo-Bonny Road project exemplifies our unwavering commitment to progress, despite significant operational and financial challenges. Extreme inflation, rising input costs, and FX volatility necessitating the declaration of Force Majeure and the suspension of works in November 2023. Nevertheless, Julius Berger resumed work in good faith in August 2024, five months before the formal execution of the contract, following a verbal agreement with the Federal Ministry of Works to adjust the contract value from NGN200 billion to NGN280 billion”.
“Although inflationary pressures on materials have risen between 200% and 600% (and even higher in some cases), the relatively modest adjustment to the contract value was a welcome step. Julius Berger’s acceptance at the time reflects our commitment to addressing challenges impacting projects and fostering mutual agreements with the Federal Government to ensure their successful delivery”, the statement further read.
Julius Berger further noted that, “The absence of a tripartite funding agreement between the Federal Government, NLNG and Julius Berger continues to impact payments, requiring Julius Berger to pre-finance significant portions of the project. Despite these challenges, we have continued to make progress, including through the yuletide season, reaffirming our commitment to delivering this critical national asset”.
“It is important to note that Julius Berger is the only contractor to have taken on this project in a challenging terrain previously abandoned by other contractors. Connecting Bonny Island to the mainland for the first time underscores our commitment to innovation and national development.
We remain focused on fostering constructive engagement with all stakeholders to ensure the timely and successful delivery of the Bodo-Bonny Road, a project critical to Nigeria’s economic and social advancement and a cornerstone for the long-term development and prosperity of the Niger Delta”, the statement read.
Rivers
Rivers High Court Restrain Trustees, Knights of St. John International, Others From Conducting Election
The High Court sitting in Port Harcourt, Rivers State, has restrained the registered trustees of Knights of St John International, Supreme Subordinate Commandery, Nigeria, and four others from conducting elections into Our Lady of Holy Rosary Local Commandery No 920 CIWA, Port Harcourt, District 48 Commandery elections, and Supreme Subordinate elections of the Knights of St John International, Nigeria, pending the determination of the substantive matters before them.
Justice G.C. Aguma and Justice V.C. Ugoji, in their separate interim orders of injunction issued in Suit No: PHC/4410/CS/2025 and Suit No: PHC/4359/CS/2025, respectively, restrained the defendants, whether by themselves, their privies, agents, servants, or any person or group of persons working under them, from conducting elections into Our Lady of Holy Rosary Local Commandery No 920, CIWA Port Harcourt, District 48 Commandery, Port Harcourt Commandery, and Supreme Subordinate of Knights of St John International, Nigeria.
The claimants, Sir Njoku Chukwuemeka Andrew and Sir Chukwuemeka Martin Mba, in separate suits, through their legal representatives, dragged the defendants to court, seeking an order to restrain them from appointing or installing any interim caretaker executive or leadership to run or pilot the affairs of St John International, Our Lady of Holy Rosary Local Commandery No 920, CIWA, Port Harcourt.
The defendants in the matter are: Registered Trustees of Knights of St John International, Supreme Subordinate Commandery, Nigeria; Brig. Gen. Emmanuel Ufuoma Okene, the Grand President, Port Harcourt Grand Commandery, Knights of St John International; Noble Brother Viktor Benebo, the Chairman Investigation Committee set up by the 2nd Defendant to investigate the claimants; Sir Architect Prempeh Ebiware, the District 48 Commander, Knights of St John International, Port Harcourt; and Sir Harry Oruma, member of Knights of St John International, Our Lady of Holy Commandery No 920, CIWA, Port Harcourt.
The two judges, after listening to the counsels in the matter, granted the claimants’ request and adjourned the matter to 10/12/2025 and 16/12/2025, respectively, for hearing of the motion on notice.