Delivering On Kalabari, Ogoni Roads
The Rivers State Government will soon get down to business on the first phase of the long-awaited Trans-Kalabari Road and the second stage of the dualisation of the Saakpenwa-Bori-Kono Road projects as both jobs have already been awarded to different contractors. The two crucial projects, costing the state government a whopping N27.6 billion, are required to be finished off within the next 14 months.
The Commissioner for Works, Eloka Tasie-Amadi, affirmed this to newsmen after a State Executive Council (SEC) meeting recently. He claimed that the Trans-Kalabari Road was 13.599 kilometres long and would be executed by Lubrik Construction Company. According to the commissioner, the road would adjoin several communities encompassing Krakrama, Omekwe-ama, Angula-ama, Mina-ama and other communities in the Kalabari area.
He said: “The project will cost N13.6 billion and will have 14 months duration, financed by irrevocable standing payment order drawn against the State Internal Revenue, meaning that every month the contractor will be paid N1 billion and there will be no delays. This will guarantee the project is not stalled and completed within the time frame stipulated and agreed with the state government. This, I believe, will be useful to the people in the area and ease their transport.”
Similarly, Tasie-Amadi revealed that the Council approved the construction of the Saakpenwa-Bori-Kono Phase 2 Road project which begins from Bori to Kono. “It is a 17-kilometre road and the cost of the project is N14 billion. Construction time is 14 months. Payment will also be secured by an irrevocable payment standing order of N1 billion monthly drawn against the State Internal Revenue”, he said.
The Works Commissioner further clarified that the Saakpenwa-Bori-Kono contract would be executed by the same firm that worked Phase 1 of the road — the Chinese Civil and Engineering Construction Corporation. He said the reason the cost of the Trans-Kalabari Road, which is 13 kilometres long and 9.3 metres wide was almost the same as that of Bori-Kono 17.1 kilometres and 24 metres wide road with a street light, was the difference in terrains.
“You see, the cost of building in the riverine area is nothing less than twice the cost of building on solid soil. So, the government is going through huge trouble to see that these roads are built. People will wonder why the cost is like that, the terrain determines the cost. So, it (Trans-Kalabari Road) is far more expensive to build,” he said.
The award of this all-important road by Governor Nyesom Wike’s administration is particularly striking and notable. We say this given that previous governments in the state had awarded the same road to indigenes of the area who were effectively mobilised, but later relinquished the work for unspecified reasons.
The significance of this road cannot be over-emphasised, as the Kalabaris will soon have a highway that criss-crosses the communities in the three local government areas of Degema, Asari-Toru and Akuku-Toru after completion. There is no doubt that this will heavily promote development and create employment opportunities for young people in the region. Having this in mind, no Kalabari person should stand in the way of this project. We recommend young people from the area to give full sanction to this cause for their benefit.
The bold decision by the governor to construct the Trans-Kalabari Road dreaded by many past governors of the state, deserves a thunderous applause. Besides the direct economic benefits of the project, the road will equally minimise rural migration to Port Harcourt from that axis of the state. Additionally, the initiative has resolved the existing around-the-clock criticisms that Wike only develops Obio/Akpor and Port Harcourt Local Government Councils.
Similarly, the second phase of the Saakpenwa-Bori-Kono Road dualisation is an attestation of Governor Wike’s affection for the Ogonis and their neighbours that stand to benefit from the project. Indeed, the project is another plus for the governor who has continually approximated his words with action. The youths, communities, Khana and Gokana people must endorse the construction and do nothing to cut back the completion of the work on record time.
As its Trans-Kalabari counterpart, the economy of the Ogonis will equally get a boost when the Saakpenwa-Bori-Kono Road is completed. It would also assist farmers for easy transportation of farm produce from rural areas to the city centres. It is noteworthy that the road has a link to five local government areas, namely; Tai, Gokana, Khana, Andoni and Opobo/Nkoro. So, there is a need to laud His Excellency for refusing to toe the line of previous administrations that deliberately declined the execution of the project even when there were sufficient funds to do it.
Saakpenwa-Bori-Kono Road is another avenue to enrich the revenue earnings of the rural dwellers in the state. Furthermore, the road would aid the speedy development of the rural communities as the movement of building materials, goods and services would be done at ease. Truly, the project will reinforce development of the area. That is why every benefitting person or community must support Wike’s vision to achieve the yearnings of Rivers people.
Both the Trans-Kalabari and Saakpenwa-Bori-Kono Roads are economically and socially invaluable. We think that there is no better time to embark on them than now. When completed, they would certainly give the people from the areas a sense of belonging. Accordingly, the state government is urged to make happen its part of the bargain with the contractors to guarantee quality work and a fitting culmination to the projects.
Editorial
Checkmating ‘One-Chance’ Menaces In PH
Editorial
That Oshiomhole’s Call On FG’s Road Projects
There are moments in the life of a legislature when plain speaking becomes a public service. Senator Adams Oshiomhole provided such a moment on the floor of the Senate when he accused the Minister of Works, Senator David Umahi, of manifestly neglecting critical federal arteries in Edo and Delta States, and implored his colleagues to prevail on the Minister to adopt a more equitable and genuinely national approach to road infrastructure delivery. It was blunt, it was uncomfortable, and it was necessary.
The specifics of his complaint deserve restating. Drawing attention to the recent approval of some 20 new road projects despite the parlous state of existing ones, the former Edo State governor lamented that Nigerians cannot travel from Benin to Warri, Benin to Asaba, Benin to Auchi, or Auchi to Okene without encountering severe distress. He alleged a deliberate omission of these corridors from the national budget in the last three years, save for palliative interventions directed by President Bola Tinubu through tax credit arrangements. His question — “What have we done wrong?” — resonates far beyond the chambers of the National Assembly.
We lend our full and unequivocal support to that call. The Auchi-Benin Road, for instance, has been in a deplorable and near-impassable condition for several years, turning what should be a two-hour journey into an all-day ordeal of broken axles, extortionate fares, and despondent commuters. The media have, on multiple occasions, chronicled the suffering of motorists, traders, and students who ply that route. To describe it as a federal road today is to stretch the meaning of the term beyond recognition.
This pattern of sidelining is not confined to Edo or Delta. Even here in Rivers State, the disposition of the Federal Ministry of Works has left much to be desired, particularly along the Eleme axis of the East-West Road. That road, which ought to be a flagship of federal presence in the Niger Delta, has remained in a wretched state for long. Those who use it daily — workers at the Eleme Petrochemical Complex, the two refineries, Onne Port, and the countless ancillary industries — can attest to its deterioration. Work has proceeded in fits and starts without the sustained urgency such a strategic road demands.
The Eleme stretch is not a mere intra-state byway. It is the gateway to the nation’s economic jugular. According to the Federal Ministry of Works and Housing’s 2023 Highway Condition Survey, only about 35 per cent of the country’s 36,000 kilometres of federal roads are rated as being in good or fair condition, with the remainder classified as poor or very poor. The East-West Road, conceived in the 1970s to bind the entire Niger Delta, remains unfinished in critical sections more than four decades after. If it had been treated as a priority, the perennial gridlock, carnage, and economic loss on the Eleme-Refinery junction would have long been consigned to history.
The irony is as painful as it is glaring. The Niger Delta remains the goose that lays the golden eggs. Data from the Nigeria Extractive Industries Transparency Initiative [NEITI 2023 Oil and Gas Audit] show that the region still accounts for over 78 per cent of Nigeria’s federally collected export earnings and about 65 per cent of total government revenue. The National Bureau of Statistics [NBS Foreign Trade Report Q4 2024] similarly confirms that crude oil continues to dominate export receipts. By every metric of equity and economic logic, a region that sustains the national purse deserves first-rate consideration in the allocation of infrastructure, not afterthoughts and tokenism.
Road infrastructure is not largesse to be dispensed by favour; it is the skeleton upon which commerce, cohesion, and citizenship hang. When contracts are concentrated in one geopolitical zone while other zones are left to contend with craters, it erodes trust in the federation itself. The World Bank’s Nigeria Development Update [June 2023] estimated that poor transport connectivity inflates the cost of moving goods by up to 40 per cent and costs the Nigerian economy an estimated $1.5 billion annually in lost man-hours and vehicle maintenance. If we profess to be one country, then equity must be the compass that guides key institutions before any project is executed. Development must spread round, not pool in one place as though other regions do not matter.
There is also a grave security dimension that can no longer be ignored. The deplorable condition of federal roads has become a veritable enabler of criminality. The NBS Crime Experience and Security Perception Survey reported over 2.5 million incidents of kidnapping-related occurrences nationally, with transport workers identifying bad road spots as prime ambush points. When vehicles are forced to crawl at 10 kilometres per hour through failed sections at Auchi, Sapele Road, or Eleme, they become sitting ducks for armed gangs. Fixing bad roads, therefore, is not merely about convenience; it is about safeguarding lives.
By his intervention, Senator Oshiomhole has hit the nail on the head and reminded Minister Umahi of a fundamental constitutional truth: public office is held in trust. The Ministry of Works is not a personal estate where contracts are awarded according to whim or political convenience. It is a national institution funded by the collective resources of Nigerians, including the oil and gas rents from the very communities whose roads are now neglected. The Minister must demonstrate balance, transparency, and a pan-Nigerian outlook in the distribution of projects that impact the daily existence of citizens. Selective neglect breeds suspicion, and suspicion is corrosive at a time when the nation is preaching unity, oneness, equity, and justice.
Consequently, the National Assembly must go beyond rhetoric and assert its oversight powers with vigour. Sections 88 and 89 of the 1999 Constitution [as amended] empower the legislature to investigate and expose any maladministration in the execution of federal projects. If an office holder is not acting rightly, it is the duty of the Senate and the House of Representatives to call him to order. Oversight must not be reduced to budget approval ceremonies; it must translate to field verification, public hearings, and insistence that the Federal Character principle, as enshrined in Section 14(3) of the Constitution, reflects in road awards.
Let the Auchi-Okene, Benin-Warri, Benin-Asaba, and Eleme East-West gangways be restored to motorable dignity. Let priority be given to completing existing, economically vital roads before embarking on new ones. If those who, through their resources, sustain the federation are sidelined in the distribution of tangible dividends, it tells poorly of our nationhood. Bad roads must be fixed, and they must be fixed now, with fairness as the guiding standard.
Editorial
Making Rivers’ 2026 Budget Count
-
News2 days agoRSG Targets Nine Million Residents in Mosquito Net Distribution Campaign
-
Oil & Energy2 days agoAiyedatiwa Signs New Electricity Bill
-
Oil & Energy2 days agoNLNG Commissions Research And Innovation Centre In RSU
-
Maritime2 days agoMarine Minister Commends President Tinubu On NPERA Bill Assent
-
News2 days agoKenPoly Holds Eight Convocations, August 29
-
News2 days agoRSG Begins Another Phase of Projects Commissioning Today
-
News2 days agoRMAFC Completes Revenue Sharing Review, Proposes New Pay
-
Maritime2 days agoNAGAFF Petitions IGP Over Alleged Maritime Police Harassment