‘Why Lagos-Ibadan Expressway Is Still 40% Completed’
As the Federal Government prepares for partial closure of the Lagos-Ibadan Expressway today for repairs, the Federal Controller of Works in Lagos, Mr Adedamola Kuti, says the project is still 40 per cent completed.
Kuti told newsmen in Lagos that the project, which began in 2013 and earlier scheduled to end in 2017, would now be completed by 2021/22 because the Muhammadu Buhari administration included some missing features.
He listed the additional features to include under passes, foot bridges, flyovers, toll plazas and road expansion.
Kuti said that the additional features shifted the completion date and made the completion level to still be at 40 per cent which it recorded months ago.
On the Ikorodu-Sagamu Road, expected to serve as an alternative route as construction work progresses on Lagos-Ibadan Expressway, Kuti said that the project was about 18 per cent completed.
He, however, added that critical sections of the highway likely to cause gridlock had been stabilised.
“The highway is about 18 per cent completed but I can tell you now for sure that there is great improvement on the road.
“What we did is, to first of all, tackle critical spots that cause traffic, and we are trying to link them up.,” he said.
He said that the ministry of Works, Housing and Power was working at night on some roads to ease gridlock.
“We have been fixing terrible but strategic roads. We are intervening here and there,’’ he said.
He noted that several road projects were abandoned in the past due to funding constraint, compelling the government to seek alternative sources of funding to fix more roads.
“A lot of projects were having difficulties getting appropriate funding but with other sources of funding, life has been brought into one or two of our projects, and that is why you are seeing activities everywhere”.
Business
Nigeria’s ETF correction deepens as STANBICETF30, VETGRIF30 see 50% decline in a week
Business
BOI Introduces Business Clinic
Business
Dangote signs $400 mln equipment deal with China’s XCMG to speed up refinery expansion
-
Maritime13 hours ago
Customs Declares War Against Narcotics Baron At Idiroko Border
-
Maritime13 hours ago
Nigeria To Pilot Regional Fishing Vessels Register In Gulf Of Guinea —Oyetola
-
Maritime13 hours ago
NIMASA,NAF Boost Unmanned Aerial Surveillance For Maritime Security
-
Maritime13 hours ago
NIWA Collaborates ICPC TO Strengthen Integrity, Revenue
-
City Crime10 hours ago
NCSU Hails Fubara Over 2025 New Telegraph Man Of The Year Award
-
Maritime13 hours ago
NIMASA GETS NEW MARITIME GUARD COMMANDER,ADOKI
-
Business13 hours agoBOI Introduces Business Clinic
-
Sports13 hours agoGombe-Gara Rejects Chelle $130,000 monthly salary