The Niger Delta Power Holding Company, NDPHC, yesterday explained that the disruptions in power supply to Eko Electricity Distribution Company, EKEDC and Aba Power Limited Electric, APLE, 14 days ago was due to maintenance issues with gas suppliers’ facilities.
The company in a statement by its Media Adviser, Mr. Adesanya Adejokun explained that the maintenance activity by its gas suppliers had a temporary impact on its operations, contributing to the temporary disruption in power supply.
Mr. Adejokun stated that, “On the morning of August 6, 2023, NDPHC received immediate instructions from the Nigeria Gas Infrastructure Company, NGIC, at approximately 08:25 hours to initiate a shutdown. This directive was prompted by ongoing maintenance work being conducted at NGIC’s Gas facilities.
“Regrettably, this maintenance work led to a significant reduction in the available gas quantity, reaching as low as 13MMscf. This quantity proved insufficient to adequately fuel our Gas turbine, which boasts a capacity of 125MW (ISO rating). Adding to these unforeseen circumstances, the Gas Aggregation Company of Nigeria, GACN, also communicated with NDPHC around 10:30 hours on the same day, August 6, 2023.
“Their notification outlined the challenges faced in gas supply along the Western axis pipeline. This pipeline is vital as it supplies gas to five of our power plants. These supply difficulties arose due to the ongoing maintenance efforts undertaken by Seplat and CNL (Chevron Nigeria Limited), our esteemed gas suppliers. The culmination of these events critically impacted gas pressure, ultimately necessitating the shutdown of all our power plants. We acknowledge the complex and interconnected nature of these challenges, and we are actively engaged with our partners to expedite the resolution of these issues and restore regular operations”, he added.
He disclosed that supply has since resumed to both distribution companies with which NDPHC has bilateral supply agreement.
“Nevertheless, on the 7th of August 2023, NDPHC’s Omotosho Power Plant achieved synchronization with the grid, precisely at 07:47 and 08:04 hours. These actions were undertaken following explicit instructions and approvals received from the National Control Centre (NCC) and NGC, respectively. A thorough review of the NCC’s daily load allocation table for the 8th of August 2023 underscores NDPHC’s unwavering commitment to meeting its contractual obligations.
“Specifically, we have consistently fulfilled our responsibilities in supplying EKEDC and APLE with the stipulated electricity capacities as delineated in the Power Purchase Agreement, PPA”.

Continue Reading

Business

Nigeria Loses N17tr Yearly To Abandoned Projects

Published

on

The Federal Government has disclosed that it has lost an estimated N17 trillion to abandoned and uncompleted projects across the country.

The Minister of State for Industry, Trade and Investment, John Enoh said this at the 8th annual induction and conference of the Chartered Institute of Project Managers of Nigeria (CIPMN).

He explained that abandoned projects continue to lock up public funds that could have been used for infrastructure development, industrial growth, job creation and essential social services.

Represented by the ministry’s Permanent Secretary, Chris Osa Isokpunwu, he said the impact goes beyond financial losses, as incomplete projects affect communities and limit access to important public services

He cited examples of  that remain unopened, schools that cannot accommodate students, roads that fail to connect communities and electricity projects that have not delivered their intended benefits.

The Registrar-General and Chief Executive Officer of CIPMN, Henry Ifeanyi Mbadiwe, also identified poor project management as a major challenge affecting development in Nigeria.

He revealed that the institute had developed a project management curriculum for Nigerian universities, which has received approval from the National Universities Commission (NUC). The programme is expected to enable universities to offer project management as a bachelor’s degree.

Mbadiwe further referenced findings by the Presidential Projects Assessment Committee, which identified 11,886 ongoing federal capital projects in 2011, with an estimated financial commitment of ?7.78 trillion.

He noted that inadequate planning, supervision, accountability and implementation were among the factors contributing to the abandonment of projects across the country.

The minister called for stronger project management structures across ministries, departments and agencies to improve planning, monitoring and evaluation.

He added that the Federal Ministry of Industry, Trade and Investment had introduced a 90-day implementation reporting cycle to strengthen transparency and monitor the progress of government programmes.

Continue Reading

Business

Transcorp Power seeks sustained investment across Nigeria’s electricity value chain

Published

on

Transcorp Power Plc Managing Director and Chief Executive Officer Peter Ikenga has called for sustained investment across Nigeria’s electricity value chain to improve power supply and make the sector self-sustaining.

Ikenga said the company remained committed to Nigeria’s power sector and would continue investing in its operations despite the challenging business environment.

He spoke in Lagos at the third edition of the Shell Power Conference, themed “Powering Nigeria’s Progress: Turning Ambition and Action into Sustainable Impact”.

The Transcorp Power chief said the company would sustain electricity generation, invest in its facilities and deliver value to shareholders.

“Transcorp Power is a long-term player, not a short-term player. This year has been challenging, but what is important is getting power to schools, hospitals and businesses to power progress,” he said.

Ikenga said the company’s focus on operational efficiency and investment had strengthened its contribution to Nigeria’s electricity supply.

He disclosed that since acquiring the Ughelli Power Plant in Delta State in 2013, Transcorp Power had quadrupled its available generation capacity.

He also said the company became the first privatised power generation firm to receive a post-privatisation discharge certificate after fulfilling all its privatisation obligations.

The company’s unaudited results for the nine months ended September 30, 2026, showed a profit before tax of N83.1 billion, while its profit-before-tax margin rose to 31.2 per cent from 29.6 per cent recorded in the corresponding period of 2025.

Its total assets rose to 11.7 per cent amounting to N629.5 billion, while shareholders’ funds grew 8.9 per cent to N199.8 billion. Cash and cash equivalents also rose to N10.3 billion, supported by improved collections.

On the company’s contribution to grid stability, Ikenga said Transcorp Power’s black-start capability enabled it to restart operations without relying on electricity from the national grid.

He explained that the capability allowed the company to support power restoration following grid disturbances, helping to restore electricity supply to homes, businesses and industries.

Ikenga noted that Nigeria had an installed electricity generation capacity of about 13,000 megawatts, with an estimated potential of 50 gigawatts, adding that realising the potential would require effective coordination across the entire value chain.

“Everything in the value chain has to work,” he said.

He called for stronger collaboration among federal and state governments, regulators and private-sector operators, alongside increased private investment, to build a sustainable electricity market.

Continue Reading

Business

FG generates N33tn revenue in 10 months – Oyedele

Published

on

The Federal Government generated a record of N33tn in revenue between January and October 2026, with improvements in digital tax administration and electronic invoicing boosting collections.
The Minister of Finance and Coordinating Minister of the Economy, Taiwo Oyedele, disclosed
this while delivering the convocation lecture at the University of Uyo, Akwa Ibom State, where he called for greater investment in Nigeria’s digital infrastructure to strengthen economic competitiveness and government revenue mobilisation.

This was contained in a statement issued on Thursday by his Senior Special Assistant on Communications and Press Secretary, Maryann Duke.

The statement said Oyedele pointed to “improved digital systems, including electronic invoicing, as a key driver behind a record of  N33tn in government revenue collected between January and October 2026.”

The minister said the performance demonstrated the potential of technology to improve revenue administration, strengthen compliance and increase efficiency across government institutions.

Speaking on the theme, ‘Digital Sovereignty and Ethics: Guarding the Economy for the Next Generation,’ Oyedele warned that Nigeria risked losing substantial economic opportunities if it continued to depend heavily on foreign digital infrastructure.

Citing Nigerian Communications Commission figures, he disclosed that the country recorded more than 157 million active internet subscriptions as of May 2026.

He explained that these connections generated significant volumes of information through financial transactions, healthcare, education and taxation.

However, citing estimates from the Nigeria Data Protection Commission, Oyedele said as much as 90 per cent of the country’s data was hosted abroad.

According to him, the situation has implications for foreign exchange expenditure, employment opportunities, technological skills and Nigeria’s control over information generated by its citizens.

He compared the country’s reliance on foreign digital infrastructure with its historical dependence on imported refined petroleum products, warning against a situation where Nigerian data would be processed abroad and the resulting services sold back to domestic users.

The minister consequently advocated greater investment in local data infrastructure, technical expertise, cybersecurity and predictable regulations to enable Nigerian businesses to capture more value from the digital economy.

He clarified that digital sovereignty should not translate into technological isolation but should strengthen Nigeria’s capacity to participate competitively in international markets.

Addressing graduating students, Oyedele urged young Nigerians to become developers of technological solutions rather than remain primarily consumers of products created elsewhere.

He identified artificial intelligence as both a disruptive force and an opportunity for innovation, advising graduates to acquire relevant digital skills alongside critical thinking, creativity, sound judgement and integrity.

The minister also cautioned against irresponsible online behaviour, explaining that digital footprints increasingly influence employment prospects, commercial relationships and professional credibility.

Oyedele outlined five priorities for graduates, including continuous learning, value creation, integrity, responsible digital citizenship and active participation in national development.

“Your degree is evidence of what you have learned. Your competence will demonstrate what you can do. Your character will reveal who you truly are,” he told the graduating students.

Continue Reading

Trending