Kaduna Refinery Rehabilitation: NNPCL, Daewoo Sign N342bn Deal
A contract sum of $740.67million has been signed between the Nigerian National Petroleum Company Limited (NNPCL) and Daewoo Engineering and Construction Nigeria Limited for the rehabilitation of Kaduna Refining and Petrochemical Company Limited (KRPC).
A release from the NNPCL revealed that the signed contract of $740.67million (N341.48billion as at Friday’s official exchange rate of N461.04/$) was signed at the Abuja headquarters of NNPC, and will last for 21 months.
According to the release, the quick-fix strategy would see to the repairs and re-streaming of KRPC, as well as ensure its operation on a sustainable basis at a minimum capacity utilisation of 60 per cent.
In the released statement, the Executive Vice President of the downstream of the national firm, Adeyemi Adetunji, was quoted as saying that the contract is marked a milestone in the history of KRPC, considering the fact that the last Turn Around Maintenance on the refinery occurred about 15 years ago, and that the project was framed after extensive engagement with Daewoo.
“This project shall be executed in three work packages as a maintenance services contract by Daewoo E&C Nigeria Limited at an estimated maximum cost ceiling of $740,669,600, with a duration of 21 months.
”The quick-fix strategy guarantees the fastest route to re-streaming Warri Refining and Petrochemical Company (WRPC) and KRPC for in-country production of refined petroleum products.
“Restoring WRPC and KRPC back to operation will guarantee energy security for the country, reduce dependence on imported petroleum products in view of near total dependence on supply of imported petroleum products and the impact the ongoing Russia-Ukraine war is having on global supply”.
“The proposed quick-fix initiative on KRPC is expected to restore it to a minimum of 60 per cent of its nameplate capacity by fourth quarter of 2024. NNPC Limited is using a combination of Internally Generated Revenue and third party financing to execute the repairs of the refineries”, he stated.
Also in the release, Adetunji noted that the rehabilitation of the Port Harcourt Refining Company had progressed considerably.
”The old refinery is currently at 64 per cent completed and the plant is expected be back in operation in second quarter of 2023, while the entre PHRC rehabilitation project currently stands at about 59 per cent.
“On the other hand, WRPC quick-fix project has achieved 28 per cent completion and is expected to be re-streamed by the end of this year”, it stated.
The statement further maintained that Nigeria should be self sufficient this year with respect to the domestic production of Premium Motor Spirit, popularly called petrol.
By: Corlins Walter
Business
Pipeline Explosion In Abua Odua, LGA Chair Calls For Calm
Business
Fidelity Bank Collaborates YEIDEP To Empower Nigerian Students
Business
NPA Launches Multi-Agency Taskforce To Combat Apapa Traffic Gridlock
-
News3 days ago
Rivers Court Jails Man Seven Years For Defiling Minor …Directs N5 Million Upkeep For Victim
-
News3 days ago
Alleged Coup Plot: DSS Docks Five For Hiding Sylva’s Whereabouts
-
News3 days agoFG To Replace NYSC Khaki With Adire
-
Niger Delta3 days ago
24 Nigerian Universities Make 2026 THE Rankings … 4 S’South Versitieis Pull Through
-
News3 days ago
BOI Unveils Maiden Impact Report, Disburses N644.9bn In 2025
-
Women3 days ago
NAWOJ Seeks Partnership With Hotel Presidential On Summit
-
News3 days agoFubara Seeks Full Resolution Of Bille Gas Leakage …Pledges Upgrade Of Community Health Centre
-
Niger Delta3 days ago
‘Ogbolo ’26’: Bayelsa Community Revives Heritage, Strengthens Unity