Connect with us

Business

Power Generation Hits 5,090MW, Highest In 2018

Published

on

Latest documents obtained from Nigeria’s Power System Operator  (SO) indicated that peak electricity generation crossed the 5,000-megawatt mark last week.
According to the SO, a peak power generation of 5,090MW was recorded on April 26, 2018, which was the highest quantum of electricity ever witnessed on the national grid since the beginning of this year.
An analysis of the documents obtained in Abuja  Friday showed that power generation started moving up gradually from the 2,298.9MW that was recorded on April 20, 2018 and peaked at 5,090MW on April 26, 2018.
It was also gathered that the average power sent out on April 26 was 4,326MWh/hour, up by 246.86MWh/h from the previous day’s figures.
The SO, however, stated that despite hitting the peak generation for the year thus far, over 2,500MW of electricity was not generated as a result of various constraints in the sector.
It outlined the major constraints in the sector as unavailability of gas, high frequency, water management issues and lack of transmission infrastructure.
The System Operator said, “On April 26, 2018, the average power sent out was 4,326MWh/hour, up by 246.86MWh/h from the previous day. A total of 1,626MW was not generated due to unavailability of gas. About 40MW was not generated due to unavailability of transmission infrastructure, while 1,075.5MW was not generated due to high frequency, resulting from unavailability of distribution infrastructure.
“About 190MW was not generated due to water management and the power sector lost estimated N1,407,000,000 on April 26, 2018 due to insufficient gas supply, distribution infrastructure, transmission infrastructure and water reserves. The dominant constraint on 26th of April 2018 remained gas, constraining a total of 1,626MW from being available on the grid. Generation peaked at the highest for 2018 at 5,090MW, and the fifth highest ever to date.”
The SO’s documents further showed that the grid had, thus far, recorded two system collapses this month.
After ensuring system stability for more than two months, the country’s power grid collapsed twice within a period of five days in April 2018.
Electricity generation figures showed that the grid recorded partial collapses on April 12 and 14 this year.
Generated power on the grid dropped from a high of 3,946.5 megawatts on April 11, to as low as 351.3MW on April 12, which was the lowest quantum of grid electricity recorded in the past two months.
Further findings showed that power generation remained in a partially collapsed state, as it only moved up marginally from the 351.3MW recorded on April 11, to 596MW on April 14.
Electricity on the grid eventually rose to 3,500MW on April 15, according to generation figures obtained from the SO.
Before the two partial collapses of this month, Nigeria’s power generation had hovered around 3,900MW for more than two months.
Industry data showed that the last system collapse before that of April 11 was recorded on the first day of February this year.
Continue Reading

Business

Nigeria Loses N17tr Yearly To Abandoned Projects

Published

on

The Federal Government has disclosed that it has lost an estimated N17 trillion to abandoned and uncompleted projects across the country.

The Minister of State for Industry, Trade and Investment, John Enoh said this at the 8th annual induction and conference of the Chartered Institute of Project Managers of Nigeria (CIPMN).

He explained that abandoned projects continue to lock up public funds that could have been used for infrastructure development, industrial growth, job creation and essential social services.

Represented by the ministry’s Permanent Secretary, Chris Osa Isokpunwu, he said the impact goes beyond financial losses, as incomplete projects affect communities and limit access to important public services

He cited examples of  that remain unopened, schools that cannot accommodate students, roads that fail to connect communities and electricity projects that have not delivered their intended benefits.

The Registrar-General and Chief Executive Officer of CIPMN, Henry Ifeanyi Mbadiwe, also identified poor project management as a major challenge affecting development in Nigeria.

He revealed that the institute had developed a project management curriculum for Nigerian universities, which has received approval from the National Universities Commission (NUC). The programme is expected to enable universities to offer project management as a bachelor’s degree.

Mbadiwe further referenced findings by the Presidential Projects Assessment Committee, which identified 11,886 ongoing federal capital projects in 2011, with an estimated financial commitment of ?7.78 trillion.

He noted that inadequate planning, supervision, accountability and implementation were among the factors contributing to the abandonment of projects across the country.

The minister called for stronger project management structures across ministries, departments and agencies to improve planning, monitoring and evaluation.

He added that the Federal Ministry of Industry, Trade and Investment had introduced a 90-day implementation reporting cycle to strengthen transparency and monitor the progress of government programmes.

Continue Reading

Business

Transcorp Power seeks sustained investment across Nigeria’s electricity value chain

Published

on

Transcorp Power Plc Managing Director and Chief Executive Officer Peter Ikenga has called for sustained investment across Nigeria’s electricity value chain to improve power supply and make the sector self-sustaining.

Ikenga said the company remained committed to Nigeria’s power sector and would continue investing in its operations despite the challenging business environment.

He spoke in Lagos at the third edition of the Shell Power Conference, themed “Powering Nigeria’s Progress: Turning Ambition and Action into Sustainable Impact”.

The Transcorp Power chief said the company would sustain electricity generation, invest in its facilities and deliver value to shareholders.

“Transcorp Power is a long-term player, not a short-term player. This year has been challenging, but what is important is getting power to schools, hospitals and businesses to power progress,” he said.

Ikenga said the company’s focus on operational efficiency and investment had strengthened its contribution to Nigeria’s electricity supply.

He disclosed that since acquiring the Ughelli Power Plant in Delta State in 2013, Transcorp Power had quadrupled its available generation capacity.

He also said the company became the first privatised power generation firm to receive a post-privatisation discharge certificate after fulfilling all its privatisation obligations.

The company’s unaudited results for the nine months ended September 30, 2026, showed a profit before tax of N83.1 billion, while its profit-before-tax margin rose to 31.2 per cent from 29.6 per cent recorded in the corresponding period of 2025.

Its total assets rose to 11.7 per cent amounting to N629.5 billion, while shareholders’ funds grew 8.9 per cent to N199.8 billion. Cash and cash equivalents also rose to N10.3 billion, supported by improved collections.

On the company’s contribution to grid stability, Ikenga said Transcorp Power’s black-start capability enabled it to restart operations without relying on electricity from the national grid.

He explained that the capability allowed the company to support power restoration following grid disturbances, helping to restore electricity supply to homes, businesses and industries.

Ikenga noted that Nigeria had an installed electricity generation capacity of about 13,000 megawatts, with an estimated potential of 50 gigawatts, adding that realising the potential would require effective coordination across the entire value chain.

“Everything in the value chain has to work,” he said.

He called for stronger collaboration among federal and state governments, regulators and private-sector operators, alongside increased private investment, to build a sustainable electricity market.

Continue Reading

Business

FG generates N33tn revenue in 10 months – Oyedele

Published

on

The Federal Government generated a record of N33tn in revenue between January and October 2026, with improvements in digital tax administration and electronic invoicing boosting collections.
The Minister of Finance and Coordinating Minister of the Economy, Taiwo Oyedele, disclosed
this while delivering the convocation lecture at the University of Uyo, Akwa Ibom State, where he called for greater investment in Nigeria’s digital infrastructure to strengthen economic competitiveness and government revenue mobilisation.

This was contained in a statement issued on Thursday by his Senior Special Assistant on Communications and Press Secretary, Maryann Duke.

The statement said Oyedele pointed to “improved digital systems, including electronic invoicing, as a key driver behind a record of  N33tn in government revenue collected between January and October 2026.”

The minister said the performance demonstrated the potential of technology to improve revenue administration, strengthen compliance and increase efficiency across government institutions.

Speaking on the theme, ‘Digital Sovereignty and Ethics: Guarding the Economy for the Next Generation,’ Oyedele warned that Nigeria risked losing substantial economic opportunities if it continued to depend heavily on foreign digital infrastructure.

Citing Nigerian Communications Commission figures, he disclosed that the country recorded more than 157 million active internet subscriptions as of May 2026.

He explained that these connections generated significant volumes of information through financial transactions, healthcare, education and taxation.

However, citing estimates from the Nigeria Data Protection Commission, Oyedele said as much as 90 per cent of the country’s data was hosted abroad.

According to him, the situation has implications for foreign exchange expenditure, employment opportunities, technological skills and Nigeria’s control over information generated by its citizens.

He compared the country’s reliance on foreign digital infrastructure with its historical dependence on imported refined petroleum products, warning against a situation where Nigerian data would be processed abroad and the resulting services sold back to domestic users.

The minister consequently advocated greater investment in local data infrastructure, technical expertise, cybersecurity and predictable regulations to enable Nigerian businesses to capture more value from the digital economy.

He clarified that digital sovereignty should not translate into technological isolation but should strengthen Nigeria’s capacity to participate competitively in international markets.

Addressing graduating students, Oyedele urged young Nigerians to become developers of technological solutions rather than remain primarily consumers of products created elsewhere.

He identified artificial intelligence as both a disruptive force and an opportunity for innovation, advising graduates to acquire relevant digital skills alongside critical thinking, creativity, sound judgement and integrity.

The minister also cautioned against irresponsible online behaviour, explaining that digital footprints increasingly influence employment prospects, commercial relationships and professional credibility.

Oyedele outlined five priorities for graduates, including continuous learning, value creation, integrity, responsible digital citizenship and active participation in national development.

“Your degree is evidence of what you have learned. Your competence will demonstrate what you can do. Your character will reveal who you truly are,” he told the graduating students.

Continue Reading

Trending