Oil & Energy
GenCos Release 3,767MW Of Electricity To National Grid
Electricity Generation Companies (GenCos), comprising gas-fired and hydro stations, said they released an average of 3,767 megawatts of electricity into the national grid last Friday.
This is contained in a daily energy report by the Advisory Power Team, Office of the Vice President, and made available to newsmen in Abuja last Saturday in Abuja.
The report said that the electricity sent out by the GenCos was up by 11.18 megawatts from the figure released last Friday.
It, however, said that 1,591 megawatts could not be generated due to unavailability of gas.
The report noted that unavailability of transmission infrastructure also accounted for non-generation of 3.0 megawatts during the period.
Similarly, it said that 2,940.60 megawatts were not generated due to high frequency resulting from unavailability of distribution infrastructure.
According to the report, zero (0) megawatts was recorded as losses due to water management procedures.
The report revealed that the power sector lost an estimated over N2 billion last Friday due to insufficient gas supply, distribution and transmission infrastructure.
On sector reform/activities, it said that the dominant constraint was high frequency resulting from unavailability of distribution infrastructure.
The report said that the peak generation attained last Friday was 4,691 megawatts.
Oil & Energy
Can Cheap Batteries Deliver COP31’s 35% Electrification Goal?
Oil & Energy
MAN, Ministry Tackle High Electricity Costs, Erratic Supply
Oil & Energy
Reps Panel Dismisses Petition Against NIPCO gas Licence
The decision followed a review by the House Sub-Committee on the Petition concerning NIPCO Plc, which rejected the complaint filed by the Nigerian Energy Security Watch Group (NESWG) for lacking substance and evidential support.
The petition had called for an investigation into, and the suspension and cancellation of, gas distribution licences issued by the Nigerian Midstream and Downstream Petroleum Regulatory Authority (NMDPRA) to NIPCO for Lagos, Ogun, Oyo and Osun states, as well as the Lagos and Lekki Free Trade Zones.
Announcing the decision last Thursday, the Chairman of the Sub-Committee, Peter Aniekwe, said the petitioners relied on hearsay and failed to establish any wrongdoing in the licensing process.
“At its sitting today, the Sub-Committee resolved not to proceed with the investigation, and the petition is accordingly dismissed,” Aniekwe said.
The committee, which also includes Dahaltu Shehu, was constituted in October to examine the petition. It was granted an additional 14 days on October 26 to conclude its assignment.
Aniekwe said the issuance and regulation of gas distribution licences were statutory responsibilities of the NMDPRA under the Petroleum Industry Act, while stressing that the National Assembly would continue to exercise oversight over the process.
He disclosed that the regulator had committed to completing and rolling out gas distribution licensing in the fourth quarter of 2026, adding that the committee would monitor the implementation.
“Nigerians deserve a gas market that is open, competitive and safe, and investors deserve rules that are clear and stable,” he said.
The lawmaker reaffirmed the House’s commitment to considering petitions from individuals and organisations with genuine concerns about the petroleum sector, saying “each complaint would be assessed on its merits”.
-
Politics2 days agoLG CITY BOY COORDINATOR HAILS WIKE’S SUPPORT FOR ONYESOH, TINUBU
-
Politics2 days ago
DIRI INAUGURATES APC CAMPAIGN COUNCIL, SETS MILLION VOTES TARGET FOR TINUBU
-
Politics2 days agoNDC Candidate Urges Oborevwori To Probe Asaba Political Violence
-
News2 days agoArmy Recovers X Account After Hack Attempt
-
Politics5 days ago
Atiku Kicks-Off 2027 Campaign, Promises To Tackle Nigeria’s Challenges
-
Featured5 days agoAPC Presidential Campaign Storms PH, ‘Morrow
-
Business2 days agoNigeria Loses N17tr Yearly To Abandoned Projects
-
News5 days ago
FG Explains Supply Disruption As Power Generation Drops To 3,659MW