TCN Committed To Power Restoration In Calabar
The Transmission Company of Nigeria (TCN) has said its engineers are working assiduously to restore power supply to Calabar, after a substation was gutted by fire.
General Manager, Public Affairs, TCN, Mrs Ndidi Mbah, made this known in a statement in Abuja.
Mbah said the fire occurred on Saturday at its Adiabo 330/132/33 KiloVolt (kV) Substation in Cross River State.
“Presently, TCN engineers are replacing the affected equipment to ensure the restoration of power to affected areas.
“Supply will be restored as soon as equipment affected by the incident is replaced, most likely, Monday evening. Investigation into the cause of the incident is already ongoing,” she said.
The TCN apologised for every inconvenience to the government and electricity customers in the State, pledging to do all it could to ensure quick restoration of bulk supply to the area.
Niger Delta
Flood: NDDC Extends Lifeline To Ayakoro Community
Niger Delta
C’River Deploys Drones To Boost Rural Healthcare Access
Niger Delta
South-South APC Elects New Zonal Executive … Reaffirms Unity Ahead Of 2027
-
Opinion3 days ago
Ozoro Festival: Tradition or Tyranny?
-
News4 days agoRSG Reiterates Commitment To Youth Dev
-
News22 hours ago
Decentralizing Pipeline Surveillance Poses Greater Dangers To Niger Delta …. Group Warns
-
Politics1 day agoAPC Resumes Electronic Membership Registration Nationwide
-
Rivers1 day agoCourt Rules Out Interim Administration In Jumbo House, Bonny
-
Oil & Energy4 days agoTranscorp Energy, Renewvia Partner On Renewable Energy Gap
-
Politics3 days ago
RIVERS WOMEN RALLY SUPPORT, CONTINUOUS PRAYERS FOR TINUBU
-
Politics3 days ago
AKPABIO, DIRI, OBOREVWORI, OTHERS VOW TO REELECT TINUBU …AS GIADOM RETAINS APC ZONAL CHAIR