Vice-President Namadi Sambo has said that two out of the four turbines at the Sapele power plant have been completed and ready for evacuation.
Sambo, who disclosed this last Friday when he inspected the Sapele power project in Delta State, said the two turbines would produce 451 megawatts of electricity.
He expressed delight with the project, saying that enormous progress had been recorded as compared to when he visited the site two years ago.
“I am happy to see that work has progressed and that two plants are being test-run right now.
“The gas facility is ready, the transmission line and the switch have been completed and are ready to evacuate power.
“I am very happy for this development. The remaining two turbines will be completed by the end of July and very soon Mr President will come to commission this project,” he said.
Sambo, who met with stakeholders and contractors of the NIPP project, encouraged them to ensure speedy completion of their contracts to enable them to attract more patronage from the government.
Earlier, Governor Emmanuel Uduaghan of Delta expressed appreciation to the Federal Government for building the thermal plant, saying that the project would enhance the state’s development.
Uduaghan maintained that the project would engage the youths in meaningful handiwork.
In his remark, the Site Manager of the company handling the project, Mr Gordon Faulker, said the entire power project in Sapele would soon be completed.
While expressing his gratitude to the government for its cooperation, Faulker said gas lines were being constructed and that the turbines would be fired as soon as gas was received in the next 40 days.
Niger Delta
CSOs, Bille Community Urge Solution To Persistent Underwater Gas Eruption
Niger Delta
Police Detain 7, Recover Arms In A’Ibom
Niger Delta
Otu Launches Grassroot Security Network In C’River
-
Editorial1 day agoDomesticate FG’s Exit Benefit Scheme
-
News1 day agoDHQ Confirms Deaths Of Terrorists, Soldiers In Borno Attack
-
News1 day agoRSU Unveils Five-Year Strategic Dev Plan …Calls For Collective Commitment To Institutional Excellence
-
News1 day agoTinubu Commissions Bayelsa Gas Turbine, Other Projects Today
-
Rivers1 day ago
Dep Gov Seeks Collaboration, Transparency Between RIVCHPP, PHCMB
-
Nation1 day ago
Rumuji Youth Leader Condemns Protest, Disowns Alleged Government Empowerment Claim
-
Business1 day ago
Niger Delta Investment Summit Targets $5bn Inflows, 500,000 Jobs
-
Featured1 day agoFG Reaffirms Nigeria’s Stability As US Embassy Suspends Visa Appointments In Abuja Office