Niger Delta
NDDC Clears Compensation Hurdle, Accelerates 3.7Km Okrika-Borikiri Bridge Project
The Niger Delta Development Commission (NDDC) has said construction work on the 3.75-kilometre Okrika-Borikiri Road and bridge project in Rivers State will gather momentum following the payment of compensation to affected property owners at the Borikiri axis of the project.
Speaking during an inspection of the project site in Okrika, the NDDC Assistant Director, Utilities, Infrastructure Development and Waterways (UIDW), Martins Isichei, disclosed that compensation issues that had stalled progress on the Borikiri alignment had been resolved.
According to him, the Commission has settled compensation claims for property owners affected by the project corridor and is awaiting the evacuation of residents before commencing demolition of structures within the right of way.
“The NDDC has paid compensation to property owners along the Borikiri alignment, and we are expecting the evacuation of residents there before we commence demolition of structures in the right of way”, he said.
Isichei noted that work on the Okrika section of the project had recorded significant progress despite challenges encountered on the waterways.
He explained that shortly after work resumed, a vessel collided with an existing pile, forcing engineers to redesign part of the bridge structure.
“When we resumed work on the site, a vessel collided with an existing pile. We had to re-profile the bridge and develop a new design to circumvent the damaged pile”, he said.
The NDDC official expressed optimism that the project would ease traffic congestion along the refinery road corridor and significantly reduce travel time between Okrika and Port Harcourt upon completion.
He explained that the project comprises three major bridge structures: the 180-metre Kolabi Bridge at Etche Waterfront, the 1,120-metre Abotoru Bridge, and the 490-metre Okpoka Bridge.
While acknowledging that progress on the Borikiri alignment had lagged because of compensation-related issues, Isichei said construction activities would commence there shortly.
Also speaking, the Project Consultant, Azu Chukwuma, said the scope of the project was reviewed following its revival to align with present realities and engineering requirements.
He noted that efforts were underway to accelerate construction, particularly the launching of bridge beams, despite the high cost of marine logistics associated with the project.
“Our intention is to determine how quickly we can proceed with launching the first sets of beams. The work is mainly on the river, and much of the marine logistics involved is costly. I am in touch with the appropriate officials of the NDDC to determine the best way forward”, Chukwuma stated.
He commended host communities for their cooperation, noting that the absence of major disputes had contributed to the project’s steady progress.
A representative of the construction company, Maroun Kassouf, said fabrication of bridge beams had advanced considerably and that installation would begin soon.
“The project is progressing well. Once people evacuate at the Borikiri end, we will demolish the structures there and move to that site immediately. That end would be much easier, as the river is shallower than the Okrika end”, he said.
The Vice Chairman of the Okrika Community Development Committee, Minengibi Ferdinand, lauded the NDDC for undertaking the project, describing it as a critical infrastructure that would improve connectivity and stimulate economic growth.
He said the road and bridge network would provide an alternative route to Okrika, ease pressure on the East-West Road and open up communities for greater socio-economic development.
“This is a laudable project that will ease traffic on the East-West Road and provide an alternate route to Okrika. We are hopeful that once it is completed, it will attract socio-economic development to our community”, Ferdinand said.