Transport

Gov Explains Revocation Of Road Contracts

Published

on

The Governor of Jigawa
State, Muhammad Badaru,  Saturday, said he revoked the  road contracts awarded by his predecessor due to incompetence and delay manifested by  contractors handling the projects.
The governor, who said this in a statement issued in Dutse by his Special Assistant on Media, Malam  Muhammad Zaki, explained that the action was not meant to stall projects initiated by the  immediate past administration in the state.
He said that the state government took the decision to terminate the contracts, based on technical advice given by the supervising ministry.
The governor said that the advice indicated that the contractors handling the projects had failed to meet stipulated standards and completion period.
According to him, the contractor collected more than a billion naira which was not commensurate with work done on ground.
The governor explained that Gagarawa-Bosuwa road of 29.75kilometres was awarded on December 16  2014 , at a contract sum of N3.7billion with an 18 month completion period.
He said that the 42-kilometre Budinga-Rambazau- Tsangarwa-Maruta-Zandam Nagogo road, was  also awarded on December 16,2014 at a contract sum ofN5billion.
He said that the first phase covering Budinga- Tsangarwa had a completion period of 12 months and both contracts were awarded to one company.
According to the governor, the company collected over Nl billion as mobilisation fee for the two projects.
“To date, only 18 kilometres of site clearing and 6.3 kilometres of filling have been carried out on Gagarawa-Bosuwa ,more than six months after mobilisation.
“ On Kila – Tsangarwa road, only five kilometers of site clearing and five kilometers of filling have been achieved, when the contractor should have reached 50 per cent completion, having been on site for six out of the 12 months completion period”, the governor said.
He said that the state government had no choice than to terminate the contract, recover public funds collected, and re-award same to a more competent and tested contractor.
Badaru said that this was being done in the interest of the communities the roads would serve.
He said that the rehabilitation of Gwaram – Basirka road, awarded in December 2014, was yet to commence because the contractor had not been mobilized to the site, and therefore, the contract had was also terminated.
Badaru stated that the action taken was necessary due to raining season that had commenced.
He said that as a result of the delay in completing the projects on schedule and the continuous rise in price of materials, govem:ment had been incurring further losses due to price variations.

Trending

Exit mobile version